• 검색 결과가 없습니다.

Project Scheduling (1)

N/A
N/A
Protected

Academic year: 2022

Share "Project Scheduling (1)"

Copied!
56
0
0

로드 중.... (전체 텍스트 보기)

전체 글

(1)

Week 6

Project Scheduling (1)

457.307 Construction Planning and Management Department of Civil and Environmental Engineering

Seoul National University

Prof. Seokho Chi shchi@snu.ac.kr

건설환경공학부 35동 304호

(2)

Project Scheduling

(PMBOK Chapter 6)

• Project Time Management

– Includes the process required to ensure timely completion of the project

• Major Processes

1. Activity definition 2. Activity sequencing

3. Activity duration estimation 4. Schedule development

5. Schedule control

(3)

Project Scheduling – Activity Definition

• WBS being the basis for development of the final activity list

• Tools and Techniques

– Decomposition

• Involves subdividing project elements into smaller, more manageable components in order to provide better

management control – Templates

• An activity list, or a portion of an activity list from a previous project, is often usable as a template for a new project

• Resource skills, required hours of effort, risk identification, expected deliverables, etc.

(4)

Project Scheduling – Activity Sequencing

• Identifying interactivity dependencies

– Precedence Diagramming Method (PDM) called Activity-On-Node (AON)

– Arrow Diagramming Method (ADM) called Activity-On-Arrow (AOA), “old school” not much used as more

(5)

Project Scheduling – Activity Sequencing

• Precedence Notation

– Activities or operations are placed on nodes – Arrows defines relationships between activities

• Finish to Start

• Start to Start

• Finish to Finish

• Start to Finish

– Apply “lags” provide ability to overlap activities, allowing the scheduler to model more accurately the project’s operation

(6)

Project Scheduling – Duration Estimate

• Estimating the number of work periods which will be needed to complete individual activities

• Tools and Techniques

– Expert judgment: historical information may be used

– Analogous estimating: called top-down estimation, means using the actual duration of a previous, similar activity

– Simulation: involves calculating multiple durations with different sets of assumptions

(7)

Project Scheduling – Duration Estimate

• Duration of an activity varies according to the activity type

– Production

• Consult subcontractors

• Calculate based on quantity and productivity

• Job conditions, new construction vs. renovation, crew size, work schedule, weather, project calendar, resource calendar – Procurement

• Consult suppliers

• Review contract documents – Administrative

• Consult agencies

• Past projects

(8)

Project Scheduling – Schedule Development

• Bar (Gantt) chart

Simple

Visual – can be checked

*Everyone can access Easily computerized

However,

sometimes difficult

to show logical connections

(9)

Project Scheduling – Schedule Development

• Matrix Schedules

Structure Metal Deck Slab Conduit Paint Carpet

B 1 2 3 4 5

start

duration

Simple

Good for repetitive work Doesn’t require computer

Hard to use for complex work

Typically useful only for part of project Difficult to define relationships

(10)

Project Scheduling – Schedule Development

• Line of Balance

Better than matrix for

(1) Repetitive activities and (2) Material

management Not good for complex project:

Difficult to make sure lines don’t cross!

(11)

Project Scheduling – Schedule Development

• Terminology

– Early Start (ES): earliest possible time an activity can start based on the logic and durations identified in the network

– Early Finish (EF): earliest possible time an activity can finish based on the logic and durations identified in the network

• EF = ES + Activity Duration

– Late Finish (LF): latest possible time an activity can finish based on the logic and durations identified in the network without extending the completion date of the project

– Late Start (LS): latest possible time an activity can start based on the logic and durations identified in the network without extending the completion date of the project

• LS = LF – Activity Duration

(12)

Project Scheduling – Schedule Development

• Terminology

– Float: additional time an activity can use beyond its normal duration and not extend the completion date of the project

• Total Float (TF): maximum time an activity can be delayed without delaying the project completion

• Free Float (FF): maximum time an activity can be delayed without delaying the start of any succeeding activity

– Critical Path: path from start to finish with no float.

Therefore, it is the minimum time to complete the project and highly impacts on the entire project schedule.

Delay in Critical Path = Project Delay!

(13)

Project Scheduling – Schedule Development

• Development Methods

– Critical Path Method (CPM): calculates a single, deterministic early and late start and finish date for each activity based on specified, sequential network logic and using duration

estimate

– Program Evaluation and Review Technique (PERT): uses sequential network logic and a weighted average duration estimate to calculate project duration

(14)

Project Scheduling – Schedule Development

• Network Forward Path Calculations – AON

– AON (precedence notation) – Finish to Start Links

• Activities without predecessors

– Early Start = 0

– Early Finish = Early Start + Activity Duration

• Activities with predecessors

– Early Start = maximum Early Finish among predecessors – Early Finish = Early Start + Activity Duration

IMPORTANT: Pay attention when working with different link types or when there are lags

(15)

Forward Path Calculation

0

Procure Forms

5 5

5

0

Mobilize

10 3

3

5

Layout Exec. 2

20 9

4 3

Layout Exc.1

15 7

4

7

Layout Exec. 3

25 11

4

7

Forms Conc. 1

30 10

3

10

Forms Conc. 2

40 13

3 12

Set Bas Plates 1

35 13

1

13

Forms Conc. 3

45 16

3

18

Set Bas Plates 3

55 19

1 15

Set Bas Plates 2

50 16

1

ES

Procure Forms

# EF

Dur. Float Legend:

SS0

SS2

SS2

FS2

FS2 FS2

EF = ES + activity duration

lag

Mobilize and procurement of forms à Concrete layout setting à Place concrete in forms à Finalize base concrete plate

(16)

Project Scheduling – Schedule Development

• Network Backward Path Calculations – AON

– AON (precedence notation) – Finish to Start Links

• Activities without successors

– Late Finish = Early Finish (or project duration) – Late Start = Late Finish – Activity Duration

• Activities with successors

– Late Finish = minimum Late Start among successors – Late Start = Late Finish – Activity Duration

(17)

Backward Path Calculation

0

Procure Forms

5 5

2 7

5

0

Mobilize

10 3

0 3

3

5

Layout Exec. 2

20 9

6 10

4 3

Layout Exc.1

15 7

3 7

4

7

Layout Exec. 3

25 11

4

7

Forms Conc. 1

30 10

7 10

3

10

Forms Conc. 2

40 13

10 13

3 12

Set Bas Plates 1

35 13

16 17

1

13

Forms Conc. 3

45 16

13 16

3

18

Set Bas Plates 3

55 19

18 19

1 15

Set Bas Plates 2

50 16

17 18

1

ES

Procure Forms

# EF

LS LF

Dur. Float Legend:

SS0

SS2

SS2

FS2

FS2 FS2

LS = LF - activity duration

(18)

Total Float Calculation

0

Procure Forms

5 5

2 7

5 2

0

Mobilize

10 3

0 3

3 0

5

Layout Exec. 2

20 9

6 10

4 1

3

Layout Exc.1

15 7

3 7

4 0

7

Layout Exec. 3

25 11

9 13

4 2

7

Forms Conc. 1

30 10

7 10

3 0

10

Forms Conc. 2

40 13

10 13

3 0

12

Set Bas Plates 1

35 13

16 17

1 4

13

Forms Conc. 3

45 16

13 16

3 0

18

Set Bas Plates 3

55 19

18 19

1 0

15

Set Bas Plates 2

50 16

17 18

1 2

ES

Procure Forms

# EF

LS LF

Dur. Float Legend:

SS0

SS2

SS2

FS2

FS2 FS2

Total Float = Late Finish – Early Finish

(19)

Critical Path

0

Procure Forms

5 5

2 7

5 2

0

Mobilize

10 3

0 3

3 0

5

Layout Exec. 2

20 9

6 10

4 1

3

Layout Exc.1

15 7

3 7

4 0

7

Layout Exec. 3

25 11

4 2

7

Forms Conc. 1

30 10

7 10

3 0

10

Forms Conc. 2

40 13

10 13

3 0

12

Set Bas Plates 1

35 13

16 17

1 4

13

Forms Conc. 3

45 16

13 16

3 0

18

Set Bas Plates 3

55 19

18 19

1 0

15

Set Bas Plates 2

50 16

17 18

1 4

ES

Procure Forms

# EF

LS LF

Dur. Float Legend:

SS0

SS2

SS2

FS2

FS2 FS2

(20)

Project Scheduling – Schedule Development

• Duration Compression

– Looks for ways to shorten the project schedule without changing the project scope

– Fast Tracking: means you look at activities normally done in sequence and assign them instead partially in parallel. For

instance, you would start construction in areas where you felt the design was pretty solid without waiting for the entire

design to be completed. Rework and Risk ↑

– Crashing: means to throw additional resources with additional costs to the critical path without necessarily getting the

highest level of efficiency. For instance, you might add a second worker to the activity usually performed by one worker. Cost ↑

(21)

Project Scheduling – Schedule Control

• Controlling changes to the project schedule

• Tools and Techniques

– Schedule change control system: includes the paperwork, tracking systems, and approval levels

– Performance measurement: assesses the magnitude of any variations

– Additional planning: due to prospective changes

(22)

Project Scheduling – Schedule Control

(23)

Project Scheduling – Schedule Control

(24)

In-Class Scheduling Exercise

• Project Start Date:

5/1/2020

Code Value Code Title

GC General

Contractor

PC Plumbing

Contractor EC Electrical

Contractor

RC Roofing

Contractor

Activity Description Duration Predecessor Code

10 Mobilization 1 GC

20 Excavation 2 10 GC

30 Place gravel 2 20 GC

40 Place slab forms 3 20 GC

50 Place rebar 2 30 GC

60 Rough in plumbing 2 50 PC

70 Pour & cure concrete 9 40, 60 GC

80 Remove forms 2 70 GC

90 Erect frame & sheath walls 4 70 GC

100 Sheath roof 3 80, 90 RC

110 Electrical 3 100 EC

120 Install siding 4 100 GC

130 Finish carpentry 3 100 GC

140 Finish roof & flashing 3 100 RC

150 Paint 5 110, 120, 130 GC

160 Clean-up 2 140, 150 GC

(25)

In-Class Exercise

1. Draw the precedence diagram network

2. Use CPM calculations to determine the project duration

3. Develop a Gantt chart

25

일 수 Activity 번호

Activity 1 Activity 2

duration float

ES

Activity

EF

LS LF

Dur. Float

1 2 3 4 5 6 7 8

duration

[예시]

ES LF

(26)

In-Class Scheduling Exercise

1. Draw the precedence diagram network

ES

Activity

EF

LS LF

Dur. Float 0

10

1

0 1

1 0

1

20

3

1 3

2 0

3

30

5

3 5

2 0

5

50

7

5 7

2 0

7

60

9

7 9

2 0

9

70

18

9 18

9 0

3

40

6

6 9

3 3

(27)

In-Class Scheduling Exercise

1. Draw the precedence diagram network

ES

Activity

EF

Dur. Float 9

70

18

9 18

9 0

18

80

20

20 22

2 2

22

100

25

22 25

3 0

25

110

28

26 29

3 1

29

150

34

29 34

5 0

34

160

36

34 36

2 0

18

90

22

18 22

4 0

25

120

29

25 29

4 0

25

130

28

26 29

3 1

25

140

28

31 34

3 6

(28)

In-Class Scheduling Exercise

2. Determine the project duration

ES

Activity

EF

LS LF

Dur. Float 0

10

1

0 1

1 0

1

20

3

1 3

2 0

3

30

5

3 5

2 0

5

50

7

5 7

2 0

7

60

9

7 9

2 0

9

70

18

9 18

9 0

3

40

6

6 9

3 3

(29)

In-Class Scheduling Exercise

2. Determine the project duration

ES

Activity

EF

Dur. Float 9

70

18

9 18

9 0

18

80

20

20 22

2 2

22

100

25

22 25

3 0

25

110

28

26 29

3 1

29

150

34

29 34

5 0

34

160

36

34 36

2 0

18

90

22

18 22

4 0

25

120

29

25 29

4 0

25

130

28

26 29

3 1

25

140

28

31 34

3 6

Duration: 36 days

C.I. = # of Critical Act /

# of Total Act

= 11/16 = 0.69

(30)

In-Class Scheduling Exercise

3. Develop a Gantt chart

(31)

Week 6

Project Scheduling (2)

457.307 Construction Planning and Management Department of Civil and Environmental Engineering

Seoul National University

Prof. Seokho Chi shchi@snu.ac.kr

건설환경공학부 35동 304호

(32)

Total Float/Free Float

• Total Float

– Most common

– Amount of movement of an activity within a window before project completion delayed

e.g., 3 days are okay to be delayed without causing a problem on a completion date

• Free Float

– Amount of movement within window before start of any succeeding activity is delayed

e.g., 3 days are okay to be delayed without causing a problem on any succeeding activity

(33)

Free Float/Total Float Comparison

Lag 3

Lag 4

A B

C Free float = min lag = 3

Total float = ??? à why?

Lag 3

Lag 4

A B

TF = 3, FF = 3 C

Don’t know completion date

(34)

Free Float/Total Float Comparison

Lag 0

B C

D

E

A

Lag 0

Lag 0 Lag 3

Lag 5

0|0

FF|TF

0|0 3|3 0|0

0|3

A, D, E on critical path C has TF = FF = 3 à why?

B has TF = 3 when FF = 0 à why?

C has TF = FF = 3 E has TF = FF = 0

(35)

Activity Relationships

• Logical connections in precedence networks

– Finish to Start (FS) – Start to Start (SS)

– Finish to Finish (FF) – Start to Finish (SF)

• FS by far most popular/used/understood

• Can include lags

– Lags are formal/required wait periods (e.g., concrete)

(36)

Finish to Finish

• Two activities must finish at same time

Position flagpole Backfill

hole Wood

facade Install windows

Ins. Ext.

Trim

FF These two must finish

at same time.

Both windows and wood must finish before exterior trim can be installed.

FF

(37)

Start to Start & Start to Finish

Spread grout

Set tile SS

These two must start at same time.

(But why wouldn’t you just model them as one activity?)

SF is a tough one! The start date of Task 1 determines the finish date of Task 2.

Usually used for procurement type activities.

Better resource allocation and management

Schedule inspection

Inspect building

(38)

Schedule Compression

• Assumptions

– Direct costs

• Are attached to activities

• Increase with decreasing duration – Indirect costs

• e.g., utilities, rent, audit and legal, administrative staffs, fuel, maintenance, security, telephone, etc.

• Independent of activity duration

• Decrease with project duration (linear costs)

(39)

Schedule Compression

• Time-Cost Trade-Off

Erect Steel

Floor Slabs

Blockwork

Fire Protection

Activity

duration direct cost curve

Indirect costs

Ignore indirect costs, so decrease duration by reducing Critical Path activities (why?)

General goal – start with lowest slope(cost/day) of cost curve (why?) To get maximum impact on schedule

Lowest slope has lowest cost deviation

(40)

Schedule Compression

• Some Terminology

– All normal: standard schedule, no compression

– Least cost: compression where least amount of increase in cost

– Least time: shortest possible project duration à reduce critical path activity

– All crash: all activities shortened à cost is greater

(41)

Schedule Compression

• Basic Steps in Compression

1. Compute schedule values for all normal schedule

2. Select critical path activity with least slope for crash costs (Least amount of increase in cost per unit time)

3. Reduce activity duration by minimum of following (= Network Interaction Limit, NIL):

1. Max days activity can be compressed

2. Min value of lags affected by activity compression

NOTE: Min value of lags for the last activity is infinity!

4. Recalculate schedule (=new all normal) with compressed activity duration (= NIL)

5. Schedule requirements met? Yes à End, No à Step 2

(42)

Schedule Compression Example (1)

0 A 1

0 1

1 0

ES # EF

LS LF

Dur. Float

1 C 6

1 6

5 0

1 B 4

3 6

3 2

6 D 9

6 9

3 0

2

Activity Max

Compression

Cost/Day

A 0 infinite

B 1 $400

C 3 $300

D 2 $150

Target: shortest possible schedule

(43)

Schedule Compression Example (1)

0 A 1

0 1

1 0

1 C 6

1 6

5 0

1 B 4

3 6

3 2

6 D 9

6 9

3 0

2

Activity Max

Compression

Cost/Day

A 0 infinite

B 1 $400

C 3 $300

D 2 $150

D has least slope (cost).

NIL(D) = min(2, Infinity) = 2

Recalculate

Min(Max days activity can be compressed,

Min value of lags affected by activity compression)

(44)

Schedule Compression Example (1)

0 A 1

0 1

1 0

1 C 6

1 6

5 0

1 B 4

3 6

3 2

6 D 7

6 7

1 0

2

Activity Max

Compression

Cost/Day

A 0 infinite

B 1 $400

C 3 $300

√D 0 $150

C has least cost

NIL(C) = min(3, 2) = 2

Recalculate

$300

Min(Max days activity can be compressed,

Min value of lags affected by activity compression)

(45)

Schedule Compression Example (1)

0 A 1

0 1

1 0

1 C 4

1 4

3 0

1 B 4

1 4

3 0

4 D 5

4 5

1 0

0

Activity Max

Compression

Cost/Day

A 0 infinite

B 1 $400

√C 1 $300

√D 0 $150

B & C now parallel critical paths.

NIL (B,C) = min(1, infinite) = 1

Recalculate

$300

$600

(46)

Schedule Compression Example (1)

0 A 1

0 1

1 0

1 C 3

1 3

2 0

1 B 3

1 3

2 0

3 D 4

3 4

1 0

0

Activity Max

Compression

Cost/Day

A 0 infinite

√B 0 $400

√C 0 $300

√D 0 $150

Total cost = $1,600

Total compression = 5 days Total duration = 4 days

$300

$900

$400

(47)

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 3 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 4 $55

F 6 5 $100 $150 1 $50

G 5 3 $320 $400 2 $40

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

A B E G

$20 $55 $40

5 C 11

9 15

6 4

5 B 15

5 15

10 0

0 A 5

0 5

5 0

5 D 13

10 18

8 5

13 F 19

18 24

6 5

15 E 24

15 24

9 0 24 G 29

24 29

5 0

4

5

Schedule Compression Example (2)

Crash Cost = Normal cost + slope

Crash Duration = Normal Duration – Day to shorten

Cost for Cycle = Cost per day * Days shorten

(48)

5 C 11

9 15

6 4

5 B 15

5 15

10 0

0 A 5

0 5

5 0

5 D 13

10 18

8 5

13 F 19

18 24

6 5

15 E 24

15 24

9 0 24 G 29

24 29

5 0

4

5

min(3, 4) = 3

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 3 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 4 $55

F 6 5 $100 $150 1 $50

G 5 3 $320 $400 2 $40

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

A B E G

$20 $55 $40

Example (2)

(49)

5 C 11

6 12

6 1

5 B 12

5 12

7 0

0 A 5

0 5

5 0

5 D 13

8 16

8 3

13 F 19

16 21

6 3

12 E 21

12 21

9 0 21 G 26

21 26

5 0

1

2

A B E G

$55 $40

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 0 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 4 $55

F 6 5 $100 $150 1 $50

G 5 3 $320 $400 2 $40

min(2, ∞) = 2

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

2 G 2 2 $40 $80 $2,060 24

Example (2)

(50)

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 0 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 4 $55

F 6 5 $100 $150 1 $50

G 5 3 $320 $400 0 $40

5 C 11

6 12

6 1

5 B 12

5 12

7 0

0 A 5

0 5

5 0

5 D 13

8 16

8 2

13 F 19

16 21

6 2

12 E 21

12 21

9 0 21 G 24

21 24

3 0

1

2

A B E G

$55

min(4, 2) = 2

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

2 G 2 2 $40 $80 $2,060 24

3 E 4 2 2 $55 $110 $2,170 22

Example (2)

(51)

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 3 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 2 $55

F 6 5 $100 $150 1 $50

G 5 3 $320 $400 2 $40

A B D E F G

$100 $55 $50

min(1, ∞) = 1

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

2 G 2 2 $40 $80 $2,060 24

3 E 4 2 2 $55 $110 $2,170 22

4 E+F 1 1 $105 $105 $2,275 21

5 C 11

6 12

6 1

5 B 12

5 12

7 0

0 A 5

0 5

5 0

5 D 13

5 13

8 2

13 F 19

13 19

6 0

12 E 19

12 19

7 0 19 G 22

19 22

3 0

1

Example (2)

(52)

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 0 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 2 $100

E 9 5 $200 $420 1 $55

F 6 5 $100 $150 0 $50

G 5 3 $320 $400 0 $40

A B D E F G

$100 $55

min(1, ∞) = 1

5 C 11

6 12

6 1

5 B 12

5 12

7 0

0 A 5

0 5

5 0

5 D 13

5 13

8 2

13 F 18

13 18

5 0

12 E 18

12 18

6 0 18 G 21

18 21

3 0

1

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

2 G 2 2 $40 $80 $2,060 24

3 E 4 2 2 $55 $110 $2,170 22

4 E+F 1 1 $105 $105 $2,275 21

5 D+E 1 1 $155 $155 $2,430 20

Example (2)

(53)

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 5 5 $100 $100 0 --

B 10 7 $500 $560 0 $20

C 6 4 $300 $400 2 $50

D 8 6 $400 $600 1 $100

E 9 5 $200 $420 0 $55

F 6 5 $100 $150 0 $50

G 5 3 $320 $400 0 $40

A B D E F G

$100

5 C 11

6 12

6 1

5 B 12

5 12

7 0

0 A 5

0 5

5 0

5 D 12

5 12

7 2

12 F 17

12 17

5 0

12 E 17

12 17

5 0 17 G 20

17 20

3 0

1

Cycle Act Can be shorten

NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $1,920 29

1 B 3 4 3 $20 $60 $1,980 26

2 G 2 2 $40 $80 $2,060 24

3 E 4 2 2 $55 $110 $2,170 22

4 E+F 1 1 $105 $105 $2,275 21

5 D+E 1 1 $155 $155 $2,430 20

Total crash cost = $510 (9-day crash) Total duration = 20 days

Example (2)

(54)

Week 6

In-Class Exercise

457.307 Construction Planning and Management Department of Civil and Environmental Engineering

Seoul National University

Prof. Seokho Chi shchi@snu.ac.kr

건설환경공학부 35동 304호

(55)

In-Class Exercise

55

C 6

B 7

A 1

D 3

I 5

H 7

K 5

J 3 F

7 E 3

G 8

ES Activity EF

Dur. Float

1. Critical Path 2. Link lag

(56)

In-Class Exercise

Cycle Act Can be shorten NIL Days shorten Cost per day Cost for cycle Total cost Project Duration

0 $5,300

56

Act. Normal Duration

Crash Duration

Normal Cost

Crash Cost

Day to Shorten

Slope ($/Day)

A 1 1 $800 $800 0 --

B 7 4 $1,000 $1,600 3 $200

C 6 4 $300 $500 2 $100

D 3 2 $400 $800 1 $400

E 3 1 $100 $200 2 $50

F 7 5 $500 $800 2 $150

G 8 4 $200 $1,400 4 $300

H 7 6 $350 $600 1 $250

I 5 3 $700 $850 2 $75

J 3 2 $500 $1,000 1 $500

K 5 4 $450 $800 1 $350

Target: shortest possible schedule 1. For the activities on the critical

path, pick the activity with least slope ($/day)

2. Reduce the duration 3. Fill out the table

Crash Cost = Normal cost + slope

Crash Duration = Normal Duration – Day to shorten

Cost for Cycle = Cost per day * Days shorten

Slope = Cost per day

참조

관련 문서

첫째, UTAUT모형을 이용하여 스마트폰 어플리케이션의 구매에 대해 검정한 결과 독립변수들 (성과기대, 예상노력, 사회적 영향, 유희적 가치,

The index is calculated with the latest 5-year auction data of 400 selected Classic, Modern, and Contemporary Chinese painting artists from major auction houses..

The key issue is whether HTS can be defined as the 6th generation of violent extremism. That is, whether it will first safely settle as a locally embedded group

1 John Owen, Justification by Faith Alone, in The Works of John Owen, ed. John Bolt, trans. Scott Clark, "Do This and Live: Christ's Active Obedience as the

CASE STUDY: SWINGLINE Foam models allowed the team to experiment with and prove out form, ergonomics, scale and proportion... CASE STUDY: SWINGLINE Creating and compiling

– Late Finish (LF): latest possible time an activity can finish based on the logic and durations identified in the network without extending the completion date of the

§ Due to the late start of construction and frequent design changes during construction, the completion of the project has been one year delayed. of the project has been

In gi ngi va,LCs are found i n oralepi thel i um ofnormalgi ngi va and i n smal l er amountsi nthesul cul arepi thel i um,buttheyareprobabl yabsentfrom thejuncti onal epi thel