Week 13

Construction IT & PMIS

457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering

Seoul National University

Prof. Seokho Chi shchi@snu.ac.kr

건설환경공학부 35동 304호

(2)

I. Construction IT & PMIS

(3)

1.1 Construction IT

(4)

1.1 Construction IT

Information Acquisition Using Technology

(5)

1.1 Construction IT

Information Acquisition Using Technology

(6)

1.1 Construction IT

Safety Management Using Mobile Computing Technology 

(7)

1.1 Construction IT

Video Computing: Automated Object Identification and Tracking 

(8)

1.1 Construction IT

Spatial Safety Assessment

(9)

1.1 Construction IT

Construction Productivity Analysis

(10)

1.1 Construction IT

건설 생산성 분석

Bucket Ready

Pour 2 Cubic Yard Load

Bucket Bucket

Empty

Load Ready

Construction Productivity Analysis

(11)

1.2 Importance for PMIS

건설프로젝트관련 정보

$10M and More General Construction Project

420 Stakeholders, 850 People,  50 Kinds of Documents, 56,000 Pages

Information on Construction Projects

(12)

1.2 Importance for PMIS

Difficulties in Information Management and Communication

Difficulties in PMIS Building and Management

– Unique objectives: Unique construction processes, information needed, management skills – Difficult to achieve uniform, standard information format

– Diverse contractors and suppliers

– Locational diversion  Possible loss of information – Individual tacit knowledge

Difficulties in Communication

– 1:1 or 1:Small knowledge sharing

– No effort for information analysis and management – Lack of lifecycle information management

*

자원관리

구매조달

전자문서관리 국한

*출처: 한대근 (2013) 정보기술 지원도 평가를 통한 건설업무 프로세스 개선에 관한 연구

(13)

1.2 Importance for PMIS

Information through Project LifeCycle

(14)

1.2 Importance for PMIS

Importance for PMIS

– Integration and categorization of construction information – Strategic information acquisition, DB building, and management

– Improve information access of construction stakeholders through web and intranet – Increase communication opportunities and knowledge enhancement

– Formation of lifecycle information feedback loop through entire project lifecycle (Best Practices, Historical DB)

Owner Request

Architect Response

Project Specification Div. 08-000

Door Hardware

A9.1 Project Schedule

Change Proposal

Schedule Impact Cost Impact Project Estimate

Hardware Schedule Door Schedule

(15)

2. Project Info. Management Systems

(16)

2.1 PMIS Sturcture

Primary Goal of PMIS

Analyze the internal operations of a corporation to increase its efficiency, effectiveness and competitiveness.

A company analysis by systematically evaluating a company’s key processes and core competencies.

Activity support using IT to adding value to the company and finally maximize the company’s profit!

(17)

2.1 PMIS Sturcture

Information Technology (IT)

– Technology itself

– e.g. server, hardware, software, etc.

– Under the information systems umbrella

Information Systems (IS)

– Large umbrella – Combination of ITs

– Systems designed to create, store, manipulate or disseminate information

Organizational Structure

– Project IS – Department IS – Enterprise-Wide IS

– Inter-organizational IS

Appliance

Server Store 3 Thin Client PC

Appliance

On-line Multi-station Store Appliance

Server Store 3 Thin Client PC

Appliance

On-line Multi-station Store

Store Location 1

Thin Client

PC PC

Thin Client

PC

In-house operations Serial Terminals

Mux Hub Unix

Enterprise Server

Unix Enterprise

Server

DIALUP/T1/T3/ISDN/FRAME RELAY

Store Location 2

DIALUP/T1/T3/ISDN/FRAME RELAY Mux

Mux

(18)

2.1 PMIS Sturcture

IS Structure Example

How can IT support strategic IS management?

Change in processes

Link with business partners (supply chain management)

Relationships with suppliers and customers

Competitive intelligence

(19)

2.1 PMIS Sturcture

Strategic IS for Company Structure

– Infrastructure Components: Hardware, Software, Data, Network, People (User), Process

Different hardware, software and data types for different people!

Day-to-day activities:

Purchase ordering systems, Inventory management systems Short-term Planning & Control:

(Project Level)

Decision Support Systems (DSS), Management Info. Systems (MIS) Long-term Planning & Control:

(Company Level) Business environment and

innovation systems,

Enterprise Info. Systems (EIS)

Strategic systems have developed to address strategic responses to changes in the business environment 

and innovation systems where the organization attempts to initiate market changes, for example, by 

beating their competitors to market with a new product or service offering.

(20)

2.1 PMIS Sturcture

Strategic IS

– Gain competitive advantage: An advantage over competitors in some measure such as cost, time or quality

– Improve core competency: Employee productivity or operational efficiency

Issues on PMIS Utilization

– Transition to e-business

– From legacy systems to corporate portals and web-based systems – How to deal with outsourcing and manage different suppliers – How much of IT infrastructure? ROI?

– The role of the developers and end users

(21)

2.1 PMIS Sturcture

Example of Web-based PMIS

(22)

2.2 PMIS Functions and Issues

PMIS and Project Lifecycle

*출처: 한국건설산업연구원 “2014 해외건설 잠재리스크 최소화를 위한 긴급토론회” ‐ 김우영

“Real Connection b/w PMIS and PM Stages is Most Important!”

(23)

2.2 PMIS Functions and Issues

Major Issues for Strategic PMIS

*출처: 한국건설산업연구원 “2014 해외건설 잠재리스크 최소화를 위한 긴급토론회” ‐ 김우영

Construction Industry Increased Size

More Competitive

Owner’s Demands

(24)

3. PM Data Mining

(25)

3.1 PM Data Mining

If we have PMIS, how can we get useful information of the information flood?

What is Data Mining?

– Knowledge discovery from data

– Extraction of interesting patterns or knowledge from huge amount of data

ALTERNATIVE NAMES

Knowledge discovery (mining) in  databases (KDD)

Knowledge extraction Data/pattern analysis Information harvesting

Data Mining in Your Life?

(26)

3.1 PM Data Mining

Information Flood

– Purchases at department/

grocery stores

– Bank/Credit card transactions – Web data, e-commerce (text

mining)

– Remote sensors on a satellite – Forecasting, risk analysis and

management

PM Data Mining

– A lot of data available

– Human analysts may take weeks to discover useful information

– Much of the data is never analysed at all

0 500,000 1,000,000 1,500,000 2,000,000 2,500,000 3,000,000 3,500,000 4,000,000

1995 1996 1997 1998 1999

The Data Gap

Total new disk (TB) since 1995

Number of

analysts

(27)

3.1 PM Data Mining

Main Objective of Data Mining: Data  Information  Knowledge

– Data

Raw description of things, events, activities and transactions that are recorded, but alone do not convey any specific meaning

e.g. 400,000

– Information

Data that have been organized so that they have meaning and value to the recipient e.g. Current $400,000 house price

– Knowledge

Information that has been organized and processed to convey understanding experience and expertise as they apply to a current problem or activity

e.g. The current $400,000 house price is cheaper than the last year’s price.

The property market may be deflated.

(28)

3.1 PM Data Mining

(1) Classification (e.g., Classifying Mammals)

(29)

3.1 PM Data Mining

(2) Association Rule Discovery

– Given a set of records each of which contain some number of items from a given collection

– Produce dependency rules which will predict occurrence of an item based on occurrences of other items

(3) Sequential Pattern Discovery

– Given is a set of objects, with each object associated with its own timeline of events, find rules that predict strong sequential dependencies among different events.

– Association rule: Concurrent events – Examples

Computer bookstore: Intro to C++  MFC using C++

(30)

3.2 Construction Applications

Pavement Management Information Systems

CS CS_Drop Roadway TRM TRM_DISP

18 -24 BI0035LK 422 1.5

58 33 BI0035LK 424 0

53 5 BI0035LK 424 0.5

56 26 BU0079BK 456 0.2

52 15 FM0112 K 556 0

20 -5 FM0112 K 556 0.5

20 1 FM0112 K 556 1

47 31 FM0112 K 556 1.5

58 24 FM0112 K 558 1.5

52 27 FM0112 K 562 1

35 -55 FM0112 K 562 1.5

53 11 FM0112 K 564 0.5

47 7 FM0112 K 564 1

48 16 FM0112 K 566 1.5

27 7 FM0112 K 568 1

28 -6 FM0112 K 568 1.5

Candidate Network-Level Project Identification

Raw PMIS Data

Potential Project List with

• Roadway ID

• TRM Information

• Condition Score

• Historical Condition Drop Score

Candidate Network-Level

Project Ranking Ranking Algorithm

(Condition-Based & Impact)

Ranked Project List with

• Roadway ID

• TRM Information

• Total Project Ranking Index

• Project Candidature Rank

PM/Rehab Decision Support

Selection Algorithm

(Project Type & Length)

Texas Department of Transportation

90% 

이상의 도로상태를

“Good or Better”

로 목표

Pavement Management Information Systems (PMIS): 4

개월에 걸친 도로포장상태 정보수집

(distress score, ride score, actual distress 

conditions, RM/PM/Rehab 

예산관련정보 등

)

(31)

3.2 Construction Applications

Processing

(32)

3.2 Construction Applications

Processing

(33)

3.2 Construction Applications

Rules

(34)

3.2 Construction Applications

Rules

(35)

3.2 Construction Applications

Data Mining

Classification Accuracy: 93%

(36)

3.2 Construction Applications

Project Ranking

0.5 VS 0.5

0.4 0.3 0.2 0.1 0.1 0.2 0.3 0.4

Score Range 0≦CS<30 30≦CS<50 50≦CS<70 70≦CS ‐10≦CSD ‐20≦CSD<‐10 ‐30≦CSD<‐20 CSD<‐30

7 FM0812 K 548 0.5 560 0 Num of 

Sections 3 10 4 0 13 4 0 0 0.29 0.12 0.23 3 17 1 2 1 10 3 194 1 0 487 1674 0

1 FM0020 K 568 0.5 578 0.5 Num of 

Sections 3 6 5 1 11 4 0 0 0.27 0.13 0.21 8 15 2 5 2 36 5 309 2 0 25 69 0

19 US0290 K 614 0.5 616 1 Num of 

Sections 0 3 1 0 2 2 0 0 0.28 0.15 0.23 4 4 7 5.5 3 7 1 350 2 0 59 0 0

8 FM1100 K 560 0 562 0 Num of 

Sections 1 2 1 0 4 0 0 0 0.30 0.10 0.22 5 4 7 6 4 5 2 48 2 0 41 125 1

18 SL0150 K 560 0.5 560 1 Num of 

Sections 0 2 0 0 0 0 2 0 0.30 0.30 0.30 1 2 13 7 5 0 0 0 0 0 34 15 1

14 SH0021 L 564 1 570 0.5 Num of 

Sections 0 0 4 5 1 3 2 3 0.14 0.28 0.20 10 9 4 7 5 12 0 6 0 0 11 1422 4

6 FM0696 K 566 1.5 566 1.9 Num of 

Sections 0 0 1 1 0 0 1 1 0.15 0.35 0.23 2 2 13 7.5 7 2 0 69 1 0 2 0 0

17 SL0109 K 434 0.5 434 1.5 Num of 

Sections 1 1 1 0 3 0 0 0 0.30 0.10 0.22 5 3 10 7.5 7 1 0 32 0 0 26 50 1

15 SH0021 R 568 0 570 0 Num of 

Sections 0 0 2 3 0 1 3 1 0.14 0.30 0.20 9 5 6 7.5 7 0 0 6 0 0 0 769 3

13 SH0021 K 580 0.5 586 0.5 Num of 

Sections 0 2 5 1 5 2 1 0 0.21 0.15 0.19 11 8 5 8 10 16 3 324 2 0 26 613 0

3 FM0535 K 552 0 564 0 Num of 

Sections 0 3 4 3 7 1 2 0 0.20 0.15 0.18 13 10 3 8 10 29 3 129 0 0 30 275 0

12 FM3000 K 560 0 560 0.5 Num of 

Sections 0 0 2 0 0 1 1 0 0.20 0.25 0.22 5 2 13 9 12 5 0 45 1 0 11 0 0

11 FM2336 K 438 0.5 444 0.5 Num of 

Sections 1 0 0 3 2 0 2 0 0.18 0.20 0.19 12 4 7 9.5 13 15 5 0 2 0 15 10 0

20 US0290 K 626 0 626 0.5 Num of 

Sections 0 0 2 0 1 1 0 0 0.20 0.15 0.18 13 2 13 13 14 1 0 192 0 0 0 0 0

5 FM0672 K 556 0 556 0.5 Num of 

Sections 0 0 2 0 1 1 0 0 0.20 0.15 0.18 13 2 13 13 14 7 7 10 2 0 7 0 0

10 FM2104 K 452 0.5 454 0 Num of 

Sections 0 0 0 3 0 1 2 0 0.10 0.27 0.17 17 3 10 13.5 16 11 1 48 0 0 0 12 0

9 FM2104 K 446 0.5 448 0.5 Num of 

Sections 0 0 2 1 1 2 0 0 0.17 0.17 0.17 18 3 10 14 17 8 2 144 0 0 2 0 0

2 FM0535 K 546 0 546 0.5 Num of 

Sections 0 0 1 1 0 2 0 0 0.15 0.20 0.17 16 2 13 14.5 18 1 0 42 0 0 0 0 0

4 FM0535 K 574 0 574 1 Num of 

Sections 0 0 2 0 2 0 0 0 0.20 0.10 0.16 19 2 13 16 19 4 0 74 0 0 15 0 0

16 SH0071 R 590 1 592 0 Num of 

Sections 0 0 0 2 0 1 1 0 0.10 0.25 0.16 19 2 13 16 19 0 0 5 0 0 15 15 0

Transverse

Deep Rut Patching Failure Block  Alligator Longitudinal

Rank        by TC

Project  Length  (PL,  Sections)

Rank        by PL

Final Score  (FS)

Final Rank  by FS

Shallow Rut

Weighting  factor

0.6 0.4

Total  Weighted 

CS Total  Weighted 

CS Drop Total  Condition 

(TC) Project 

Number Roadway 

ID

Beginning  Reference  Marker

Displace‐

ment Ending  Reference 

Marker Displace‐

ment

Project's PMIS Data Condition Score (CS) Condition Score Drop (CSD) Weighting Factor Final Result Distress Summation

AREA 1 AREA 2 AREA 3 AREA 4 AREA 5 AREA 6

참조

관련 문서

4013.407 Construction Technology A Sudy on Project Resource &amp; information Management with Internet Application

It aimed to help students access background information that can facilitate subsequent reading, provide specific information needed for successful

출처: “국내 건설 적산 제도” (한국건설산업연구원 최석인 연구위원). 457.308 Construction

41 Developing Web Intelligence System of Construction Tacit Knowledge Based on Text

 management of the flow of information, products, and services across management of the flow of information, products, and services across a network of customers,

“Simplifying Simulation Modeling through Integration with 3D CAD.” Journal of Construction Engineering and Management, Volume 126, Issue 6, pp.

– Unique objectives: Unique construction processes, information needed, management skills – Difficult to achieve uniform, standard information format.. – Diverse

– Organizational support for safety education (e.g. orientation, training, workshops, etc.) for all level of project members – Regular safety meetings and daily toolbox