Week 8
Project Cost Estimating (1)
457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering
Seoul National University
Prof. Seokho Chi shchi@snu.ac.kr
건설환경공학부 35동 304호
Estimating Construction Costs
• Approaches to estimating
• Conceptual / Detailed estimating
• RS Means data and examples
• Estimates
– Necessary to guide decisions, budgets – Hard to do well
– Are performed by several actors
• Owners
• Designers
• Contractors
• Subcontractors
Bid Estimate
Total Project Cost
(총 공사원가)
Construction Cost
(순 공사원가)
Overhead
(일반관리비)
Profit
(이윤)
Material Cost
(재료비)
Labor Cost
(노무비)
Expenses
Accounting/Admin fees, (경비) Advertising, Insurance, Interest, Legal fees, Rent, Repairs, Taxes, Telephone
bills, Travels, etc.
5-6% of construction cost
Construction-related expenses:
Equipment, Maintenance, Electricity, Transportation, Waste control, Consulting, R&D cost, Testing, Inventory, etc.
Maximum 15% of Sum(Labor cost, Expenses, Overhead)
Feasibility Analysis
Design
Procurement
Construction
Turnover (Handover)
Operations &
Maintenance
Disposal (Reuse) Need (desire)
Conceptual Estimating
ROM (Rough-Order of Magnitude)
= cost per unit of capacity, +/- 20%
e.g., # of beds in a hospital,
# of rooms in a hotel
Square Foot/Cubic Foot
= cost per sq/cf of building type, +/-15%
Detailed Estimating
Assemblies
= per WBS component cost, +/- 10%
e.g., foundation (excavation, formwork, reinforcing, concrete, etc.)
Quantity Take-Off
= per unit cost, +/- <5%
Context: Project Timeline
Design
Program- ming
Schematic
Design development
Construction documents
ROM
SF/CF
Assemblies
70% complete
100% complete
Use costs to iterate design concepts
Predict final costs
Unit Pricing
• Preparation Time X Accuracy
Cost Estimating
Conceptual Estimating
• Guide decisions regarding: location, scope, feasibility.
• Very little project information is available
• Size of the project is generally known, although it may be described in terms of capacity (e.g.: number of beds, megawatts)
• Short preparation time
• Estimates prepared for many different program options
Detailed Estimating
• Based on a (near) complete set of documents
• Owner team prepares an estimate to negotiate
• Contractors prepare an estimate to bid (or negotiate)
• Price given by contractors for different work packages
may be based on bids from pre-qualified subcontractors
Conceptual Estimating
• Consideration
– Building type – Location
– Rough size – Material type – Time
• Compare to historical data (similar buildings)
– Apply modifiers as needed
Bid Estimate
• Resources for Estimate
– U.S.
• RS Means Building Construction Cost Data
• RS Means Assemblies Cost Data
• RS Means Square Foot Costs – Australia
• Rawlinsons Construction Cost Guide – Korea
• 표준품셈 (대한건설협회): provide quantity information of activities
• 실적공사비 (한국건설기술연구원): provide historical database
RS Means Building Data
• Compiles info
• Good starting point
• Firm data often better (why?)
Example:
Library - 6,500 sf
RS Means - $97.30/sf
Estimated cost : $632,450 If ¼, 25% of that type of building costs less than the indicated price and 75%
costs more
Building Costs
Location Indices
100 = National Average MAT: Material Cost, INST: Labor Cost
(1) ROM Estimate
• 100-bed dormitory (low rise); median quality; 2003 data; in Nashville, TN; Jan 2003 construction start
– Total cost = Number of units × Unit cost
= 100 units × 36,300 per unit
= $3,630,000 (without adjustments)
• Location Adjustment
– National average city index = 100
– Adjusted cost for a city = Estimated cost × City index / 100 – For Nashville: 86.2
– Adjusted total cost = $3,630,000 × 86.2 / 100
= $3,129,060
(2) SF Estimate – Modeled
• 19,386 ft
2fire station; face brick with concrete block back-up; steel joists; 2003 data; in Austin;
January 2005 construction start; 2.5% projected increase per year.
– Total cost = Size in ft2 × Cost/ft2
= 19,386 ft2 × $97.95/ft2 (approximately)
= $1,898,858 (without adjustments)
(2) SF Estimate – Modeled (Cont’d)
• Add-on Features:
– Combination range, refrigerator, sink, microwave oven &
icemaker (quantity = 1) = 1 × $5,275
– Steel lockers, single tier, 72” (8 openings) = 8 × $200
• Cost with add-on features = $ 1,905,733
• Key point
– Estimates can mix level of detail
• If you find, you can add now
– Danger is to double count
• You need to figure out which one has been included already through itemized building code
• Clearly determine included/not-included items
(2) SF Estimate – Modeled (Cont’d)
• Location Adjustment
– National average city index = 100
– Adjusted cost for a city = Estimated cost × City index / 100 – For Austin
• Adjusted Austin cost = $ 1,905,733 × 79.7 / 100
= $1,518,869
(2) SF Estimate – Modeled (Cont’d)
• Time Adjustment
– 2003 data used for 2005 construction
– Time adjusted cost = (1 + % projected yearly increase)n × Adjusted Cost
= (1 + 0.025)2 * $1,518,869
= $1,595,761
Detailed Estimating
• Scope definition
– Dimensions, specified quality, construction methodology, potential problems and solutions
• Quantity take off
– Packaging of project components’ scope into units that can be priced
• Pricing
– Applying marketplace labor, material, and equipment costing to the quantities
– Factors such as schedule, construction process, productivity, labor agreements, and resource allocation should be considered
• Overhead and profit issues
– Overhead, profit, sales taxes, labor benefits, bond, and contingency
Scope Definition
• Contract documents
– Drawings
– Specifications
– Technical references – Addenda
• Site analysis
– Soil
– Utilities – Access – Neighbors
– Existing structures
• New construction vs. Repair and remodeling
• Bonding and insurance requirements
Basic Detailed Process
• Estimated Cost =
Quantity × Price (material + installation) per unit
• Quantity: by counting
• Price: by time, materials, and crew cost
– Materials: vendor data
– Crew cost: varies by composition of junior and senior members as well as size; also equipment
– Time (duration): by productivity per unit
» Can vary a lot by method, crew size
Estimate Setup
• Format
• Organization of cost items
• Separation of subcontractors from in-house work
• Adjustments
• Overhead and profit (markup) summary
• Estimate summary
}
Typically by CSI codesQuantity Take Off
• Break a project down into work packages (e.g., excavate for spread footings, place concrete for spread footings)
– This can be really hard!
• Determine quantity for work package
– Requires a strong understanding of the work involved – Be careful with details, scales, and units
– Take advantage of repeated project elements
– Make sure you don’t quantify the same element twice – Account for waste, shrinkage, swell, equipment wear
Unit Pricing
• Sources of pricing information
– Publications – In-house data
– Material suppliers
– Equipment rental companies – Subcontractors
– Unions
– Government offices
– Insurance and bonding providers
Unit Pricing (Cont’d)
• Material Costs:
– Specifications (e.g.: model number, color, finish) – Price valid until delivery time
– Delivery
– Warranties and guarantees – Lead time to delivery
– Supplier’s stock
– Supplier’s reputation
– Payment terms Important to control to prevent negative cash flow!
Unit Pricing (Cont’d)
• Labor Costs:
– Wage rate
• Trade
• Union vs. Non-Union
• Project location
• Fringe
– Productivity
• Crew efficiency
• Concurrent work
• Weather conditions
• Workspace
• Regular vs. overtime
Washington State Carpenters (sample)
Journeyman
Regular Time
Time & a Half
Rate $27.95 $41.93
Health 2.90 2.90
Pension 3.87 3.87
Apprentice 0.35 0.35
Total Fringe 7.12 7.12
Taxable Wage Rate 35.07 49.05
FICA @ 7.65% 2.14 3.21
State Unem. @ 5.42% 1.51 2.27
Fed. Unem. @ 0.8% 0.22 0.34
Workers Comp @
$2.0859/hr
2.09 2.09
Total Payroll Taxes &
Insurance
5.96 7.91
Labor Burden (fringe + tax
& ins)
13.08 15.03
Total Labor Rate 41.03 56.96
*Total Fringe: Health + Pension + Apprentice FICA: Federal Insurance Contributions Act
Unit Pricing (Cont’d)
• Equipment Costs
– Cost of ownership, lease, or rental
• Interest
• Storage
• Insurance
• License
• Taxes – Operation
• Gasoline/oil
• Maintenance
• Transportation
• Mobilization
• Operator (may be included with labor)
• Item-by-item basis vs. project basis
Overhead and Profit
• Job organization
• Travel expenses
• Engineering support
• Marketing, legal, and accounting fees
• Testing
• Equipment (project basis)
• Field office
• Temporary utilities
• Permits
• Temporary roads
• Insurance and bonds
• Clean up
• Safety
devices/signs/barricades
• Photographs
• Taxes (other than direct costs)
Profit: Markup on above, 3-10% typical (tends to be higher in housing)
In Class Exercise
• In Austin:
1. Find the estimated cost of putting in place 500 lf of 10’
high large columns
2. Find the estimated installation cost of 10 25’x25’ waffle slab bays with a 75 psf load
3. Find the cost of elevated floors on a 5 story (5 stories with 4 elevated floors and a roof) apartment block with
10,000sf/floor. Slab on grade construction.
RS Means
In Class Exercise
1. Find the estimated cost of putting in place 500 lf
(linear foot = regular feet)
of 10’ high large columns
In Class Exercise
2. Find the estimated installation cost of 10 25’x25’
waffle slab bays with a 75 psf load
In Class Exercise
3. Find the cost of elevated floors on a 5 story (5 stories with 4 elevated floors and a roof) apartment block with 10K sf/floor. Slab on grade construction.
5 4 3 2 1
Roof
Slab on Grade
Elevated Floor
Bid Estimate
• 표준품셈
– Provide material quantity, labor hour information for given construction activities in standard construction environment – Yearly updated by 50 review committees
Mixing Ratio (배합용적비) Cement (시멘트, kg) Sand (모래, m3) Labor (인부, 인) 1 : 1
1 : 3 1 : 5
1,093 510 320
0.78 1.10 1.15
1.0 1.0 0.9
(m3당) Civil 6-1-2 Mortar
Bid Estimate
• 일위대가 (Itemized Unit Cost)
– Quantity identified from 표준품셈 X Cost from 일위대가
• Estimate
(공사비 내역서)(m3당) Mortar 1:1 Mixing Ratio
Item Size Unit Quantity Material Cost Labor Cost Expenses Total
Others
Unit \ \ Unit \ \ Unit \ \ \
Cement KG 1,093 80 87,440
Sand ㎡ 0.78 11,000 8,580
Labor Person 1 57,820 57,820
Total 96,020 57,820 153,840
Activity
(공종) Type Unit Quantity (물량)
Material Cost Labor Cost Expenses Total
Unit \ \ Unit \ \ Unit \ \ Unit \ \
Mortar 1:1 ㎥ 10 96,020 960,200 57,820 578,200 - - 153,840 1,538,400
~
Total 000 000
(단위: 원)
Bid Estimate
• 일위대가 (Itemized Unit Cost)
– Material cost: Government cost info + Market cost info
(조달청 발행 가격정보, 물가자료 또는 물가정보)
– Labor cost: Construction Association of Korea yearly
collects labor cost information from 50-60 construction sites and announces standardized labor cost every 1st of January
(대한건설협회 고시 노임단가, 50-60개 현장을 대상으로 년1회 실사 후 매년 1월1일 공표)
Bid Estimate
• Estimate U-Type Side Gutter
(U형 측구)Cost
Bid Estimate
• 표준품셈 vs 실적공사비
Rebar Installation
Formwork
Concrete
(Contract Cost DB)
Life Cycle Costing – Overview
• Background
– Context, need
– Definitions: LCC, LCA – Range of practice
– Resources
• Refresher: Discounting
• LCC Methods
– Steps/overview methodology – Inputs/considerations
– Calculation methods
• Examples/Extensions
Background
• Life-cycle approaches
– Estimate projects through the entire project life-cycle
– Grew from a need to better understand and approach costs holistically
• Owners didn’t know what expenses they were committing to when making capital investments
– Augment traditional investment decisions with considerations of future expense flows such as maintenance, environmental costs, etc.
– Are practiced
• Ex: Building donors often now solicited for maintenance funds as well as capital costs
Total Building Costs
Capital Energy Security
Maintenance &
Replacement
Adapted from Life Cycle Assessment – A Primer, Paladino Consulting LCC, July 2000, Seattle, WA, www.palcon.com
LCC & LCA
• LCC – Life Cycle Costing
– Considers all costs pertinent to the acquisition, operation, maintenance and disposition of a facility
• LCA – Life Cycle Assessment
– Encompassed LCC considerations but also the performance and environmental burdens and costs associated with a given facility
LCA
• Life Cycle Assessment is a process to evaluate the
environmental burdens associated with a product, process, or activity by identifying energy and materials used and
wastes released to the environment;
– to assess the impact of those energy and materials used and releases to the environment; and
– to identify and evaluate opportunities to affect environmental improvements.
• The assessment includes the entire life cycle of the product, process or activity, encompassing, extracting, and
processing raw materials; manufacturing, transportation and distribution; use, re-use, maintenance; recycling and final
disposal.
LCA vs LCC
• LCA is truly holistic
• LCC more clearly identified as costs impacting a single organization (typically an owner)
• LCC is an established methodology
– Uses investment analysis to compare costs over a defined period
• Boundary between LCC and LCA unclear
– e.g., How do you incorporate additional investment in facility quality on staff productivity improvements?
LCC Practice
• LCC methodology encompasses:
– Capital costs – O&M costs
• Energy in particular – Salvage costs
• Contains methods to obtain, collect, and process input data for the above
• Is extensible to allow assessment of any
considerations with quantifiable costs
LCC Practice
• Federally mandated for new and leased buildings
– National Energy Conservation Policy Act (1978)
– Federal Energy Management Improvement Act (1988)
• Moved to most states and municipal governments
– e.g., Wisconsin (1982)
• Now practiced in some form by most major
corporations and institutional owners for major
capital investments
LCA Practice – LEED Standards
• LEED (Leadership in Energy and Environmental Design) Green Building Rating System
– LEED provides a complete framework for assessing building performance and meeting sustainability goals
• define "green building" by establishing a common standard of measurement
• promote integrated, whole-building design practices
• recognize environmental leadership in the building industry
• stimulate green competition
• raise consumer awareness of green building benefits
• transform the building market
Korea: 친환경 건축물 인증 by 국토해양부, 환경부 since 2005 (greenbuilding.re.kr)
LCA Practice – LEED Standards
• LEED Green Building Rating System
– Categories
• Sustainable sites: erosion control, urban redevelopment, reduced site disturbance, landscape, etc.
• Water efficiency: wastewater management, water use reduction, etc.
• Energy and atmosphere: minimum energy performance, renewable energy, ozone depletion, green power, etc.
• Material and resources: building reuse, resource reuse, renewable materials, certified wood, etc.
• Indoor environmental quality: CO2 monitoring, ventilation, indoor chemical and pollutant sources, thermal comfort, etc.
• Innovation and design process: innovation in design, LEED professional, etc.
Net Present Value (NPV) Analysis
• Discounting: $ tomorrow is worth less than $ today
– Why?
Cash Flow Mapping
P
0 1 2 3 4 5…. n
F A
P: present value (year 0) F: future value at year n
A: annual return (at year’s end) i: interest rate per period
n: number of years/periods Rule 1: Always start at year 0!
(present time or start of study period)
Rule 2:
Ignore expenses before study period (sunk costs).
Rule 3: always compare alternatives using the same study period
Rule 4: use a common sign convention
+ _
If you can get the cash flow diagram straight, you have the problem mostly solved!
Discounting or NPV Formulas
F|P
(P to F)F = P(1+i)
nP|F P = 1/(F|P)
F|A
(A to F)F = A[((1+i)
n)-1)/i]
A|F A = 1/(F|A)
P|A
(A to P)P = A [((1+i)
n)-1)/(i(1+i)
n)]
A|P A = 1/(P|A)
P
0 1 2 3…. n
A F
NPV = Net Present Value
NPV Example
• Repair vs Replace HVAC system
– If repair current HVAC,
• no upfront costs (P=0), but O&M costs are $100k/yr
– If replace with new HVAC,
• upfront costs are $300k and O&M costs are $50k/yr
– Assume 10 year lifespan, i = 7%
NPV Example (Cont’d)
• Repair
• Replace
P=0
0 1 2 3 4 5…. 10
A=-$100k/yr
NPV = 0 + P|A = 0 + (-$702k) = -$702k
P=-$300k
0 1 2 3 4 5…. 10
A=-$50k/yr
NPV = -300 + P|A = -$300k + (-$351k) = -$651k
Makes sense to invest in the new system!
P|A = A [((1+i)n)-1)/(i(1+i) n)]
Inflation Happens
…and it adds up
Source: US Dept of Labor Bureau of Labor Statistics www.bls.gov
CPI (Consumer Price Index) All items/Urban: 1913-2004
The Corrosive Effect of Inflation
• Suppose 3% inflation for 30 years
– $1 purchasing power today à
F|P, 3%, 30 yrs à Need $2.43 tomorrow
• Suppose 4% inflation for 30 years
– $1 today à Need $3.24 tomorrow
What does this do to your estimate for retirement savings?
Discount Rates and Inflation
• Discount rate accounts for time value of money
– Real interest: Rate after inflation
– Nominal interest: Rate inclusive of inflation – Nominal ≈ Real + Inflation rate (approximate)
• Cash flows
– Constant dollars: No inflation, dollars expected to be same as base date (time=0, thinking from Present)
e.g., $100 O&M costs: In 2030, actually pay $100+α – Current dollars: Account for inflation in each period
e.g., $1,000 home mortgage: In 2030, actually still pay $1,000
*Real interest rate 4%: inflation이 있어도4%의 이자
*O&M Cost of $400: 현재로 봤을 때400불이란 얘기지 실제로 그때가 되면 더 낼 수가 있다.
Discount Rates and Inflation
• Use
– Real interest rate with constant dollars
– Nominal interest rate with current dollars
– Example: real rate = 4%, inflation rate = 3%, annual income of $100k/yr in constant dollars
0 1 2 3 4 5…. n
0 1 2 3 4 5…. n
current,
nominal ≈ 7%
If n = 10, NPV ≈ $810
constant, real = 4%
If n = 10, NPV ≈ $810
103
109 113 106
116 100*(1.03)^n 100
PV’s are Same!
Exponential Gradient Series Cash Flow
P|EG
(EG to P)P = EG[(z
n-1)/(z
n(z-1))], z=(1+i)/(1+g)
cf. Uniform Gradient Series Cash Flow P|G
(G to P)P = G[((1+i)
n-1)/(i
2×(1+i)
n)-n/(i×(1+i)
n)]
0 1 2 3 4 5…. n
103
109 113 106
116 100*(1.03)^n
Cool about Real Interest
• You can ignore inflation!
– Make estimates in constant dollars – Everything is scaled to today’s prices
– Is more accurate: inflation varies, but real returns more stable
*Real return: Real interest provides increase in money in the future after taking account of inflation increase
e.g., $100 O&M costs: In 2030, actually pay $100+α