• 검색 결과가 없습니다.

Project Cost Estimating (1)

N/A
N/A
Protected

Academic year: 2022

Share "Project Cost Estimating (1)"

Copied!
59
0
0

로드 중.... (전체 텍스트 보기)

전체 글

(1)

Week 8

Project Cost Estimating (1)

457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering

Seoul National University

Prof. Seokho Chi shchi@snu.ac.kr

건설환경공학부 35동 304호

(2)

Estimating Construction Costs

• Approaches to estimating

• Conceptual / Detailed estimating

• RS Means data and examples

• Estimates

– Necessary to guide decisions, budgets – Hard to do well

– Are performed by several actors

• Owners

• Designers

• Contractors

• Subcontractors

(3)

Bid Estimate

Total Project Cost

(총 공사원가)

Construction Cost

(순 공사원가)

Overhead

(일반관리비)

Profit

(이윤)

Material Cost

(재료비)

Labor Cost

(노무비)

Expenses

Accounting/Admin fees, (경비) Advertising, Insurance, Interest, Legal fees, Rent, Repairs, Taxes, Telephone

bills, Travels, etc.

5-6% of construction cost

Construction-related expenses:

Equipment, Maintenance, Electricity, Transportation, Waste control, Consulting, R&D cost, Testing, Inventory, etc.

Maximum 15% of Sum(Labor cost, Expenses, Overhead)

(4)

Feasibility Analysis

Design

Procurement

Construction

Turnover (Handover)

Operations &

Maintenance

Disposal (Reuse) Need (desire)

Conceptual Estimating

ROM (Rough-Order of Magnitude)

= cost per unit of capacity, +/- 20%

e.g., # of beds in a hospital,

# of rooms in a hotel

Square Foot/Cubic Foot

= cost per sq/cf of building type, +/-15%

Detailed Estimating

Assemblies

= per WBS component cost, +/- 10%

e.g., foundation (excavation, formwork, reinforcing, concrete, etc.)

Quantity Take-Off

= per unit cost, +/- <5%

Context: Project Timeline

(5)

Design

Program- ming

Schematic

Design development

Construction documents

ROM

SF/CF

Assemblies

70% complete

100% complete

Use costs to iterate design concepts

Predict final costs

Unit Pricing

(6)

• Preparation Time X Accuracy

Cost Estimating

(7)

Conceptual Estimating

• Guide decisions regarding: location, scope, feasibility.

• Very little project information is available

• Size of the project is generally known, although it may be described in terms of capacity (e.g.: number of beds, megawatts)

• Short preparation time

• Estimates prepared for many different program options

(8)

Detailed Estimating

• Based on a (near) complete set of documents

• Owner team prepares an estimate to negotiate

• Contractors prepare an estimate to bid (or negotiate)

• Price given by contractors for different work packages

may be based on bids from pre-qualified subcontractors

(9)

Conceptual Estimating

• Consideration

– Building type – Location

– Rough size – Material type – Time

• Compare to historical data (similar buildings)

– Apply modifiers as needed

(10)

Bid Estimate

• Resources for Estimate

– U.S.

• RS Means Building Construction Cost Data

• RS Means Assemblies Cost Data

• RS Means Square Foot Costs – Australia

• Rawlinsons Construction Cost Guide – Korea

• 표준품셈 (대한건설협회): provide quantity information of activities

• 실적공사비 (한국건설기술연구원): provide historical database

(11)

RS Means Building Data

• Compiles info

• Good starting point

• Firm data often better (why?)

Example:

Library - 6,500 sf

RS Means - $97.30/sf

Estimated cost : $632,450 If ¼, 25% of that type of building costs less than the indicated price and 75%

costs more

Building Costs

(12)

Location Indices

100 = National Average MAT: Material Cost, INST: Labor Cost

(13)

(1) ROM Estimate

• 100-bed dormitory (low rise); median quality; 2003 data; in Nashville, TN; Jan 2003 construction start

– Total cost = Number of units × Unit cost

= 100 units × 36,300 per unit

= $3,630,000 (without adjustments)

• Location Adjustment

– National average city index = 100

– Adjusted cost for a city = Estimated cost × City index / 100 – For Nashville: 86.2

– Adjusted total cost = $3,630,000 × 86.2 / 100

= $3,129,060

(14)

(2) SF Estimate – Modeled

• 19,386 ft

2

fire station; face brick with concrete block back-up; steel joists; 2003 data; in Austin;

January 2005 construction start; 2.5% projected increase per year.

– Total cost = Size in ft2 × Cost/ft2

= 19,386 ft2 × $97.95/ft2 (approximately)

= $1,898,858 (without adjustments)

(15)

(2) SF Estimate – Modeled (Cont’d)

• Add-on Features:

– Combination range, refrigerator, sink, microwave oven &

icemaker (quantity = 1) = 1 × $5,275

– Steel lockers, single tier, 72” (8 openings) = 8 × $200

• Cost with add-on features = $ 1,905,733

• Key point

– Estimates can mix level of detail

• If you find, you can add now

– Danger is to double count

• You need to figure out which one has been included already through itemized building code

• Clearly determine included/not-included items

(16)

(2) SF Estimate – Modeled (Cont’d)

• Location Adjustment

– National average city index = 100

– Adjusted cost for a city = Estimated cost × City index / 100 – For Austin

• Adjusted Austin cost = $ 1,905,733 × 79.7 / 100

= $1,518,869

(17)

(2) SF Estimate – Modeled (Cont’d)

• Time Adjustment

– 2003 data used for 2005 construction

– Time adjusted cost = (1 + % projected yearly increase)n × Adjusted Cost

= (1 + 0.025)2 * $1,518,869

= $1,595,761

(18)

Detailed Estimating

• Scope definition

– Dimensions, specified quality, construction methodology, potential problems and solutions

• Quantity take off

– Packaging of project components’ scope into units that can be priced

• Pricing

– Applying marketplace labor, material, and equipment costing to the quantities

– Factors such as schedule, construction process, productivity, labor agreements, and resource allocation should be considered

• Overhead and profit issues

– Overhead, profit, sales taxes, labor benefits, bond, and contingency

(19)

Scope Definition

• Contract documents

– Drawings

– Specifications

– Technical references – Addenda

• Site analysis

– Soil

– Utilities – Access – Neighbors

– Existing structures

• New construction vs. Repair and remodeling

• Bonding and insurance requirements

(20)

Basic Detailed Process

• Estimated Cost =

Quantity × Price (material + installation) per unit

• Quantity: by counting

• Price: by time, materials, and crew cost

– Materials: vendor data

– Crew cost: varies by composition of junior and senior members as well as size; also equipment

– Time (duration): by productivity per unit

» Can vary a lot by method, crew size

(21)

Estimate Setup

• Format

• Organization of cost items

• Separation of subcontractors from in-house work

• Adjustments

• Overhead and profit (markup) summary

• Estimate summary

}

Typically by CSI codes

(22)

Quantity Take Off

• Break a project down into work packages (e.g., excavate for spread footings, place concrete for spread footings)

– This can be really hard!

• Determine quantity for work package

– Requires a strong understanding of the work involved – Be careful with details, scales, and units

– Take advantage of repeated project elements

– Make sure you don’t quantify the same element twice – Account for waste, shrinkage, swell, equipment wear

(23)

Unit Pricing

• Sources of pricing information

– Publications – In-house data

– Material suppliers

– Equipment rental companies – Subcontractors

– Unions

– Government offices

– Insurance and bonding providers

(24)

Unit Pricing (Cont’d)

• Material Costs:

– Specifications (e.g.: model number, color, finish) – Price valid until delivery time

– Delivery

– Warranties and guarantees – Lead time to delivery

– Supplier’s stock

– Supplier’s reputation

– Payment terms Important to control to prevent negative cash flow!

(25)

Unit Pricing (Cont’d)

• Labor Costs:

– Wage rate

• Trade

• Union vs. Non-Union

• Project location

• Fringe

– Productivity

• Crew efficiency

• Concurrent work

• Weather conditions

• Workspace

• Regular vs. overtime

Washington State Carpenters (sample)

Journeyman

Regular Time

Time & a Half

Rate $27.95 $41.93

Health 2.90 2.90

Pension 3.87 3.87

Apprentice 0.35 0.35

Total Fringe 7.12 7.12

Taxable Wage Rate 35.07 49.05

FICA @ 7.65% 2.14 3.21

State Unem. @ 5.42% 1.51 2.27

Fed. Unem. @ 0.8% 0.22 0.34

Workers Comp @

$2.0859/hr

2.09 2.09

Total Payroll Taxes &

Insurance

5.96 7.91

Labor Burden (fringe + tax

& ins)

13.08 15.03

Total Labor Rate 41.03 56.96

*Total Fringe: Health + Pension + Apprentice FICA: Federal Insurance Contributions Act

(26)

Unit Pricing (Cont’d)

• Equipment Costs

– Cost of ownership, lease, or rental

• Interest

• Storage

• Insurance

• License

• Taxes – Operation

• Gasoline/oil

• Maintenance

• Transportation

• Mobilization

• Operator (may be included with labor)

• Item-by-item basis vs. project basis

(27)

Overhead and Profit

• Job organization

• Travel expenses

• Engineering support

• Marketing, legal, and accounting fees

• Testing

• Equipment (project basis)

• Field office

• Temporary utilities

• Permits

• Temporary roads

• Insurance and bonds

• Clean up

• Safety

devices/signs/barricades

• Photographs

• Taxes (other than direct costs)

Profit: Markup on above, 3-10% typical (tends to be higher in housing)

(28)

In Class Exercise

• In Austin:

1. Find the estimated cost of putting in place 500 lf of 10’

high large columns

2. Find the estimated installation cost of 10 25’x25’ waffle slab bays with a 75 psf load

3. Find the cost of elevated floors on a 5 story (5 stories with 4 elevated floors and a roof) apartment block with

10,000sf/floor. Slab on grade construction.

RS Means

(29)

In Class Exercise

1. Find the estimated cost of putting in place 500 lf

(linear foot = regular feet)

of 10’ high large columns

(30)

In Class Exercise

2. Find the estimated installation cost of 10 25’x25’

waffle slab bays with a 75 psf load

(31)

In Class Exercise

3. Find the cost of elevated floors on a 5 story (5 stories with 4 elevated floors and a roof) apartment block with 10K sf/floor. Slab on grade construction.

5 4 3 2 1

Roof

Slab on Grade

Elevated Floor

(32)

Bid Estimate

• 표준품셈

– Provide material quantity, labor hour information for given construction activities in standard construction environment – Yearly updated by 50 review committees

Mixing Ratio (배합용적비) Cement (시멘트, kg) Sand (모래, m3) Labor (인부, 인) 1 : 1

1 : 3 1 : 5

1,093 510 320

0.78 1.10 1.15

1.0 1.0 0.9

(m3당) Civil 6-1-2 Mortar

(33)

Bid Estimate

• 일위대가 (Itemized Unit Cost)

– Quantity identified from 표준품셈 X Cost from 일위대가

• Estimate

(공사비 내역서)

(m3당) Mortar 1:1 Mixing Ratio

Item Size Unit Quantity Material Cost Labor Cost Expenses Total

Others

Unit \ \ Unit \ \ Unit \ \ \

Cement KG 1,093 80 87,440

Sand 0.78 11,000 8,580

Labor Person 1 57,820 57,820

Total 96,020 57,820 153,840

Activity

(공종) Type Unit Quantity (물량)

Material Cost Labor Cost Expenses Total

Unit \ \ Unit \ \ Unit \ \ Unit \ \

Mortar 1:1 10 96,020 960,200 57,820 578,200 - - 153,840 1,538,400

~

Total 000 000

(단위: 원)

(34)

Bid Estimate

• 일위대가 (Itemized Unit Cost)

– Material cost: Government cost info + Market cost info

(조달청 발행 가격정보, 물가자료 또는 물가정보)

– Labor cost: Construction Association of Korea yearly

collects labor cost information from 50-60 construction sites and announces standardized labor cost every 1st of January

(대한건설협회 고시 노임단가, 50-60개 현장을 대상으로 년1회 실사 후 매년 1월1일 공표)

(35)

Bid Estimate

• Estimate U-Type Side Gutter

(U형 측구)

Cost

(36)

Bid Estimate

• 표준품셈 vs 실적공사비

Rebar Installation

Formwork

Concrete

(Contract Cost DB)

(37)

Life Cycle Costing – Overview

• Background

– Context, need

– Definitions: LCC, LCA – Range of practice

– Resources

• Refresher: Discounting

• LCC Methods

– Steps/overview methodology – Inputs/considerations

– Calculation methods

• Examples/Extensions

(38)

Background

• Life-cycle approaches

– Estimate projects through the entire project life-cycle

– Grew from a need to better understand and approach costs holistically

• Owners didn’t know what expenses they were committing to when making capital investments

– Augment traditional investment decisions with considerations of future expense flows such as maintenance, environmental costs, etc.

– Are practiced

• Ex: Building donors often now solicited for maintenance funds as well as capital costs

(39)

Total Building Costs

Capital Energy Security

Maintenance &

Replacement

Adapted from Life Cycle Assessment – A Primer, Paladino Consulting LCC, July 2000, Seattle, WA, www.palcon.com

(40)

LCC & LCA

• LCC – Life Cycle Costing

– Considers all costs pertinent to the acquisition, operation, maintenance and disposition of a facility

• LCA – Life Cycle Assessment

– Encompassed LCC considerations but also the performance and environmental burdens and costs associated with a given facility

(41)

LCA

• Life Cycle Assessment is a process to evaluate the

environmental burdens associated with a product, process, or activity by identifying energy and materials used and

wastes released to the environment;

– to assess the impact of those energy and materials used and releases to the environment; and

– to identify and evaluate opportunities to affect environmental improvements.

• The assessment includes the entire life cycle of the product, process or activity, encompassing, extracting, and

processing raw materials; manufacturing, transportation and distribution; use, re-use, maintenance; recycling and final

disposal.

(42)

LCA vs LCC

• LCA is truly holistic

• LCC more clearly identified as costs impacting a single organization (typically an owner)

• LCC is an established methodology

– Uses investment analysis to compare costs over a defined period

• Boundary between LCC and LCA unclear

– e.g., How do you incorporate additional investment in facility quality on staff productivity improvements?

(43)

LCC Practice

• LCC methodology encompasses:

– Capital costs – O&M costs

• Energy in particular – Salvage costs

• Contains methods to obtain, collect, and process input data for the above

• Is extensible to allow assessment of any

considerations with quantifiable costs

(44)

LCC Practice

• Federally mandated for new and leased buildings

– National Energy Conservation Policy Act (1978)

– Federal Energy Management Improvement Act (1988)

• Moved to most states and municipal governments

– e.g., Wisconsin (1982)

• Now practiced in some form by most major

corporations and institutional owners for major

capital investments

(45)

LCA Practice – LEED Standards

• LEED (Leadership in Energy and Environmental Design) Green Building Rating System

– LEED provides a complete framework for assessing building performance and meeting sustainability goals

• define "green building" by establishing a common standard of measurement

• promote integrated, whole-building design practices

• recognize environmental leadership in the building industry

• stimulate green competition

• raise consumer awareness of green building benefits

• transform the building market

Korea: 친환경 건축물 인증 by 국토해양부, 환경부 since 2005 (greenbuilding.re.kr)

(46)

LCA Practice – LEED Standards

• LEED Green Building Rating System

– Categories

• Sustainable sites: erosion control, urban redevelopment, reduced site disturbance, landscape, etc.

• Water efficiency: wastewater management, water use reduction, etc.

• Energy and atmosphere: minimum energy performance, renewable energy, ozone depletion, green power, etc.

• Material and resources: building reuse, resource reuse, renewable materials, certified wood, etc.

• Indoor environmental quality: CO2 monitoring, ventilation, indoor chemical and pollutant sources, thermal comfort, etc.

• Innovation and design process: innovation in design, LEED professional, etc.

(47)

Net Present Value (NPV) Analysis

• Discounting: $ tomorrow is worth less than $ today

– Why?

(48)

Cash Flow Mapping

P

0 1 2 3 4 5…. n

F A

P: present value (year 0) F: future value at year n

A: annual return (at year’s end) i: interest rate per period

n: number of years/periods Rule 1: Always start at year 0!

(present time or start of study period)

Rule 2:

Ignore expenses before study period (sunk costs).

Rule 3: always compare alternatives using the same study period

Rule 4: use a common sign convention

+ _

If you can get the cash flow diagram straight, you have the problem mostly solved!

(49)

Discounting or NPV Formulas

F|P

(P to F)

F = P(1+i)

n

P|F P = 1/(F|P)

F|A

(A to F)

F = A[((1+i)

n

)-1)/i]

A|F A = 1/(F|A)

P|A

(A to P)

P = A [((1+i)

n

)-1)/(i(1+i)

n

)]

A|P A = 1/(P|A)

P

0 1 2 3…. n

A F

NPV = Net Present Value

(50)

NPV Example

• Repair vs Replace HVAC system

– If repair current HVAC,

• no upfront costs (P=0), but O&M costs are $100k/yr

– If replace with new HVAC,

• upfront costs are $300k and O&M costs are $50k/yr

– Assume 10 year lifespan, i = 7%

(51)

NPV Example (Cont’d)

• Repair

• Replace

P=0

0 1 2 3 4 5…. 10

A=-$100k/yr

NPV = 0 + P|A = 0 + (-$702k) = -$702k

P=-$300k

0 1 2 3 4 5…. 10

A=-$50k/yr

NPV = -300 + P|A = -$300k + (-$351k) = -$651k

Makes sense to invest in the new system!

P|A = A [((1+i)n)-1)/(i(1+i) n)]

(52)
(53)

Inflation Happens

(54)

…and it adds up

Source: US Dept of Labor Bureau of Labor Statistics www.bls.gov

CPI (Consumer Price Index) All items/Urban: 1913-2004

(55)

The Corrosive Effect of Inflation

• Suppose 3% inflation for 30 years

– $1 purchasing power today à

F|P, 3%, 30 yrs à Need $2.43 tomorrow

• Suppose 4% inflation for 30 years

– $1 today à Need $3.24 tomorrow

What does this do to your estimate for retirement savings?

(56)

Discount Rates and Inflation

• Discount rate accounts for time value of money

– Real interest: Rate after inflation

– Nominal interest: Rate inclusive of inflation – Nominal ≈ Real + Inflation rate (approximate)

• Cash flows

– Constant dollars: No inflation, dollars expected to be same as base date (time=0, thinking from Present)

e.g., $100 O&M costs: In 2030, actually pay $100+α – Current dollars: Account for inflation in each period

e.g., $1,000 home mortgage: In 2030, actually still pay $1,000

*Real interest rate 4%: inflation이 있어도4%의 이자

*O&M Cost of $400: 현재로 봤을 때400불이란 얘기지 실제로 그때가 되면 더 낼 수가 있다.

(57)

Discount Rates and Inflation

• Use

– Real interest rate with constant dollars

– Nominal interest rate with current dollars

– Example: real rate = 4%, inflation rate = 3%, annual income of $100k/yr in constant dollars

0 1 2 3 4 5…. n

0 1 2 3 4 5…. n

current,

nominal ≈ 7%

If n = 10, NPV ≈ $810

constant, real = 4%

If n = 10, NPV ≈ $810

103

109 113 106

116 100*(1.03)^n 100

PV’s are Same!

(58)

Exponential Gradient Series Cash Flow

P|EG

(EG to P)

P = EG[(z

n

-1)/(z

n

(z-1))], z=(1+i)/(1+g)

cf. Uniform Gradient Series Cash Flow P|G

(G to P)

P = G[((1+i)

n

-1)/(i

2

×(1+i)

n

)-n/(i×(1+i)

n

)]

0 1 2 3 4 5…. n

103

109 113 106

116 100*(1.03)^n

(59)

Cool about Real Interest

• You can ignore inflation!

– Make estimates in constant dollars – Everything is scaled to today’s prices

– Is more accurate: inflation varies, but real returns more stable

*Real return: Real interest provides increase in money in the future after taking account of inflation increase

e.g., $100 O&M costs: In 2030, actually pay $100+α

참조

관련 문서

This study collects and analyzes data on the historical construction cost of steel box girder bridges, identifies key cost impact factors, provides two approximate

Step 2: The second step in a life-cycle assessment is to inventory the outputs that occur, such as products, byproducts, wastes and emissions, and the inputs, such as raw

Basic aspects of AUTOSAR architecture and methodology Safety mechanisms supported by AUTOSAR.. Technical safety concepts supported by AUTOSAR Relationship to ISO

First, it examines the music environment in the 20th century and developmental process of technical improvements and materials used which allowed for the

Directed Energy Deposition (DED) processes selectively dissolve and solidify the material using a high density energy source to produce a desired product. In

457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering..

– Crew cost: varies by composition of junior and senior members as well as size; also equipment. – Time (duration): by

• LCC computes Present Value of alternatives over a period of time using discounting methods.. • Hence, important to consider alternatives using same period of