• 검색 결과가 없습니다.

458.401 Process & Product Design

N/A
N/A
Protected

Academic year: 2022

Share "458.401 Process & Product Design"

Copied!
20
0
0

로드 중.... (전체 텍스트 보기)

전체 글

(1)

06

Jong Min Lee

School of Chemical and Biological Engineering Seoul National University

Estimation of 
 Capital Costs

Estimation of Capital Costs 06

Project Cost Estimation

• Bill of Material (B/M) -

견적서

• Total Investment Cost (TIC)

-

Fixed Investment Capital (FIC) + Working Capital (WC)

• Fixed Capital Investment (고정투자비)

-

All the costs associated with building the plant

-

Most of FIC depreciated except land

• Working Capital (시운전동안 안정적으로 운전하기 위한 비용)

-

The amount of capital required to start up the plant and finance the first few months of operation before revenues from the process start

-

15 ~ 25% of the fixed capital investment

(2)

Types of Capital Cost Estimates

1. Order-of-Magnitude Estimate (Feasibility) - AACE Class 5 - +40%, -20%

- BFD, process modification (이전의 공장을 가지고 capa비교 산정)

2. Study Estimate / Major Equipment - AACE Class 4 - +30%, -20%

- PFD, cost chart, roughly sized major equipment

3. Preliminary Design (Scope) Estimate - AACE Class 3 - +25%, -15%

- PFD, vessel sketches, equip. diagrams, plot plan / Major equip. + piping + instr. + elec. + util

4. Definitive (Project Control) Estimate - AACE Class 2 - +15%, -7%

- PFD, P&ID, all vessel sketches, equip. diagrams, preliminary isometrics

3

Estimation of Capital Costs 06

Types of Capital Cost Estimates

5. Detailed (Firm or Contractors) Estimate - AACE Class 1 - +6%, -4%

- Everything included - ready to go to construction phase

- Complete engineering, vendor quote

• Estimate low so actual cost will be high (+)

• Estimate high so actual cost will be low (-)

• Why is + # > -# ?

(3)

5

Estimation of Capital Costs 06

Example-01

The estimated capital cost for a chemical plant using the study estimate method (Class 4) was calculated to be $2 million. If the plant were to be built, over what range would you expect the actual capital estimate to vary?

Solution-01

Lowest Expected Cost Range

(4)

7

Example-01

The estimated capital cost for a chemical plant using the study estimate method (Class 4) was calculated to be $2 million. If the plant were to be built, over what range would you expect the actual capital estimate to vary?

Solution-01

Highest Expected Cost Range

Estimation of Capital Costs 06

Capital Cost Estimate

• Order of Magnitude (Rule of Thumb) - Based on the plant capacity

‣ Production rate or feed processing rate

- Typical figure (example)

‣ $2,500/kW for coal fired power plant

‣ $25,000/bpsd of crude oil processing in the refinery complex plant

Cost Curve

- Capacity of process unit as the x-axis and the cost as the y- axis in the log-log chart

- Cost calculation basis: the scope of plant

(5)

Capacity Factored Estimate (CFE)

9

The plant capital cost (by Lang): based on the variation in the plant size

Plant A Cost

Plant B Cost = Plant A Capacity Plant B Capacity

n

n

: between 0.5 and 0.85, and 0.6 in average (Accuracy: 25~50%)

exponent, n Type of Chemical Plant

0.8~0.9 Gas compression plant with many machineries (Methanol plant) 0.7 Petrochemical plant

0.4~0.5 Small plant, but instrumentation is well provided 0.6 Average value for most chemical plants

Estimation of Capital Costs 06

Capacity Factored Estimate (CFE)

CFE Formula for Refinery Process Units

<latexit sha1_base64="Lhib887t5D+gVFY9YApMt+inL6k=">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</latexit>

Capital Cost (MM$) = ↵ ⇥ capacity

Process Unit 𝜶 β Unit

ADU 8.20 0.510 1,000 bpsd

VDU 8.34 0.493 1,000 bpsd

Delayed Coker, 10 bbl feed/ton coke 17.56 0.657 1,000 bpsd Delayed Coker, 30 bbl feed/ton coke 24.42 0.644 1,000 bpsd

FCC 24.67 0.461 1,000 bpsd

RFCC 32.98 0.510 1,000 bpsd

Hydrocracker, 1000 scf/bbl H2 15.65 0.719 1,000 bpsd

Hydrocracker, 3000 scf/bbl H2 26.18 0.714 1,000 bpsd

NHT 4.96 0.524 1,000 bpsd

DHT 8.62 0.576 1,000 bpsd

ARDS 8.61 0.834 1,000 bpsd

CCR 12.19 0.547 1,000 bpsd

(6)

Capacity Factored Estimate (CFE)

11

CFE Formula for Refinery Process Units

<latexit sha1_base64="Lhib887t5D+gVFY9YApMt+inL6k=">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</latexit>

Capital Cost (MM$) = ↵ ⇥ capacity

Process Unit 𝜶 β Unit

C4 Isomerization 9.57 0.514 1,000 bpsd

C5/C6 Isomerization, once through 3.11 0.565 1,000 bpsd

C5/C6 Isomerization, recycle 6.17 0.599 1,000 bpsd

Alkylation 12.19 0.606 1,000 bpsd

H2 Production, Steam methane reforming 3.35 0.599 MMscfd

Partial oxidation 5.44 0.601 MMscfd

Gas Processing, 1 gal/Mscf 1.91 0.627 MMscfd

Gas Processing, 10 gal/Mscf 4.38 0.593 MMscfd

Gas Processing, 20 gal/Mscf 5.83 0.610 MMscfd

Amine Gas Treating 0.064 0.746 MMscfd

SRU 0.064 0.746 ton/day

Estimation of Capital Costs 06

Capacity Factored Estimate (CFE)

CFE Formula for Chemical Process Unit

Plant A Cost

Plant B Cost = Plant A Capacity Plant B Capacity

n

Chemical Process Unit Exponent (n)

AN 0.6

BD 0.68

Chlorine 0.45

Ethanol 0.73

EO 0.78

HCl 0.68

Hydrogen Peroxide 0.75

Methanol 0.60

Nitric Acid 0.60

Chemical Process Unit Exponent (n)

Phenol 0.75

PP 0.70

PVC 0.60

Sulfuric Acid 0.65

Styrene 0.60

Urea 0.65

Vinyl Acetate 0.80

(7)

Estimating Purchased Equip. Costs

• Vendor quote

- Most accurate

‣ based on specific information

‣ requires significant engineering

• Use previous cost on similar equipment and scale for time and size

- Reasonably accurate

‣ beware of large extrapolation

‣ beware of foreign currency

• Use cost estimating charts and scale for time

- Less accurate

- Convenient

13

Estimation of Capital Costs 06

Effect of Size: Equipment Factored Estimate (EFE)

C a C b =

✓ A a A b

◆ n

<latexit sha1_base64="cZv1oexqHqrQxk7zvuzLSIIfUbc=">AAACG3icbZDLSgMxFIYz9VbrrerSTbAU6qbMVEE3Qks3LivYC3RqyaSZNjSTGZIzQhn6Hm58FTcuFHEluPBtTNtZaOuBhJ//yyHn/F4kuAbb/rYya+sbm1vZ7dzO7t7+Qf7wqKXDWFHWpKEIVccjmgkuWRM4CNaJFCOBJ1jbG9dnvP3AlOahvINJxHoBGUruc0rAWP18xfUVoUm9T6bm8qb4GruC+VDCC1CbgZoBruLDEZzdS9zPF+yyPS+8KpxUFFBajX7+0x2ENA6YBCqI1l3HjqCXEAWcCjbNubFmEaFjMmRdIyUJmO4l892muGicAfZDZY4EPHd/dyQk0HoSmMmLAYGRXmYz8z/WjcG/6iVcRjEwSRcf+bHAEOJZUHjAFaMgJkYQqriZFdMRMZmAiTNnQnCWV14VrUrZOS/btxeFajWNI4tO0CkqIQddoiq6QQ3URBQ9omf0it6sJ+vFerc+Fk8zVtpzjP6U9fUDIEGg1A==</latexit>

Cost

Equipment Cost Attribute - Size

Cost Exponent (7.1)

C

<latexit sha1_base64="GFeDDFRDHdoAXhf1g3ErnaMzxI0=">AAAB9XicbVDLSgMxFL1TX7W+qi7dBIvgqsyooBuh0o3gpoJ9QDstmTTThiaZIckoZeh/uHGhiFv/xZ1/Y9rOQlsPXO7hnHvJzQlizrRx3W8nt7K6tr6R3yxsbe/s7hX3Dxo6ShShdRLxSLUCrClnktYNM5y2YkWxCDhtBqPq1G8+UqVZJB/MOKa+wAPJQkawsVK32sPoGt2hG9u7slcsuWV3BrRMvIyUIEOtV/zq9COSCCoN4VjrtufGxk+xMoxwOil0Ek1jTEZ4QNuWSiyo9tPZ1RN0YpU+CiNlSxo0U39vpFhoPRaBnRTYDPWiNxX/89qJCa/8lMk4MVSS+UNhwpGJ0DQC1GeKEsPHlmCimL0VkSFWmBgbVMGG4C1+eZk0zsreedm7vyhVKlkceTiCYzgFDy6hArdQgzoQUPAMr/DmPDkvzrvzMR/NOdnOIfyB8/kD/G6Q3w==</latexit>

a = KA n a (7.2)

where K = C b A n b

<latexit sha1_base64="exPzpN5Ktn7aEalLz4X9J3V+se0=">AAAB/nicbVDLSsNAFL2pr1pfUXHlZrAIrkqigm6ESjeCmwr2AW0Mk+mkHTqZhJmJUELAX3HjQhG3foc7/8bpY6GtBy4czrmXe+8JEs6Udpxvq7C0vLK6VlwvbWxube/Yu3tNFaeS0AaJeSzbAVaUM0EbmmlO24mkOAo4bQXD2thvPVKpWCzu9SihXoT7goWMYG0k3z64RVeoG0pMspof5Nm1HzyI3LfLTsWZAC0Sd0bKMEPdt7+6vZikERWacKxUx3US7WVYakY4zUvdVNEEkyHu046hAkdUednk/BwdG6WHwliaEhpN1N8TGY6UGkWB6YywHqh5byz+53VSHV56GRNJqqkg00VhypGO0TgL1GOSEs1HhmAimbkVkQE2WWiTWMmE4M6/vEiapxX3rOLenZer1VkcRTiEIzgBFy6gCjdQhwYQyOAZXuHNerJerHfrY9pasGYz+/AH1ucPMjiVAA==</latexit>

a: equipment with the required attribute b: equipment with the base attribute n: varies between 0.30 and 0.84. often around 0.6 (six-tenth rule)

Note: 본 방법이 플랜트 전체 투자 비용 산정에 쓰인다면 Capacity Factored Estimate (CFE)으로 불리운다.

Table 7.3

(8)

15

With the six-tenths rule, the % increase in purchased cost when the capacity of a piece of equipment is doubled will be

C a /C b = (2/1) 0.6 = 1.52

<latexit sha1_base64="/U1b3CQSUvmlQGwBl+2WoTKsF0U=">AAACB3icbVDLSgMxFM3UV62vUZeCBItQN9NJfW6EQjcuK9gHtOOQSTNtaOZBkhHK0J0bf8WNC0Xc+gvu/BvTdhbaeuDCyTn3knuPF3MmlW1/G7ml5ZXVtfx6YWNza3vH3N1ryigRhDZIxCPR9rCknIW0oZjitB0LigOP05Y3rE381gMVkkXhnRrF1AlwP2Q+I1hpyTUPay6GZVhzPXgNS5UyOrlPbetirF/IOq+4ZtG27CngIkEZKYIMddf86vYikgQ0VIRjKTvIjpWTYqEY4XRc6CaSxpgMcZ92NA1xQKWTTu8Yw2Ot9KAfCV2hglP190SKAylHgac7A6wGct6biP95nUT5V07KwjhRNCSzj/yEQxXBSSiwxwQlio80wUQwvSskAywwUTq6gg4BzZ+8SJoVC51a6PasWK1mceTBATgCJYDAJaiCG1AHDUDAI3gGr+DNeDJejHfjY9aaM7KZffAHxucP5maU2w==</latexit>

Even though the equipment capacity was doubled, the purchased cost of the equipment increased by only 52%.

__________________: The larger the equipment, the lower the cost of equipment per unit of capacity

Estimation of Capital Costs 06

Example-02

A new plant ordered a set of floating head heat exchangers (area = 100 m 2 ) cost $92,000. What would cost be for a heat exchanger for similar service if area = 50 m 2 and n = 0.44?

Solution-02

K = C b

A n b = 92, 000

100 0.44 = 12, 128

<latexit sha1_base64="1wh4ttsMj3Xm3Ke4hw9IXdDfKvk=">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</latexit>

(9)

Effect of Time

• Time increases - cost increases (inflation)

• Inflation is measured by cost indexes (Fig. 7.3)

- Chemical Engineering Plant Cost Index (CEPCI); our textbook uses this

- Marshall and Swift Process Industry Index (generally accepted)

• Numbers based on basket of goods typical for construction of chemical plants (Table 7.5)

17

Estimation of Capital Costs 06

Location Factor

• Transportation cost

Taxes

• Labor supply and local productivity

• Codes and local inspection

Country Region Location Factor

Russia 1.53

India 1.02

ME 1.07

China Imported 1.12

Indigenous 0.61

US Gulf Coast 1.00

(10)

Equation for Time Effect

19

C 2 = C 1

✓ I 2 I 1

<latexit sha1_base64="GNPEKyt2829A00oenwkadEAZBcI=">AAACEXicbVDLSsNAFJ34rPUVdelmsAh1U5Iq6EYodKO7CvYBTQiT6aQdOnkwcyOUkF9w46+4caGIW3fu/BunbRbaeuBeDufcy8w9fiK4Asv6NlZW19Y3Nktb5e2d3b198+Cwo+JUUtamsYhlzyeKCR6xNnAQrJdIRkJfsK4/bk797gOTisfRPUwS5oZkGPGAUwJa8sxq06vja9z0bOwIFkAVO4EkNLv16rludo4dyYcjOPPMilWzZsDLxC5IBRVoeeaXM4hpGrIIqCBK9W0rATcjEjgVLC87qWIJoWMyZH1NIxIy5Wazi3J8qpUBDmKpKwI8U39vZCRUahL6ejIkMFKL3lT8z+unEFy5GY+SFFhE5w8FqcAQ42k8eMAloyAmmhAquf4rpiOiEwEdYlmHYC+evEw69Zp9XrPvLiqNRhFHCR2jE1RFNrpEDXSDWqiNKHpEz+gVvRlPxovxbnzMR1eMYucI/YHx+QPZIZst</latexit>

C = Cost

I = Value of cost index

1, 2 = Represents points in time at which costs required or known and index values known

Example-03

Cost of vessel in 1996 was $25,000, what is estimated cost in 2010?

Solution-03

$25, 000 ⇥

✓ 551 382

= $36, 000

<latexit sha1_base64="5ZgYyisUvUtgsVMJUxTaYfh7k5Y=">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</latexit>

Estimation of Capital Costs 06

Example-04

2 heat exchangers, 1 bought in 1990 and the other in 1995 for the same service

A B

Area 70 m 2 130 m 2

Time 1990 1995

Cost 17,000 24,000

I 358 381

What is the cost of a 80m 2 heat exchanger today? (I = 582)

(11)

21

Solution-04

Cost today (A) = (Cost in 1990) ⇥ (Capacity Correction) ⇥ (Inflation Correction)

= 17, 000 ⇥ (80/70) 0.59 ⇥ (582/358)

= 29, 900

<latexit sha1_base64="ivs9+Vd9G469xLLbjV+14bidd7k=">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</latexit>

Cost today (B) = (Cost in 1995) ⇥ (Capacity Correction) ⇥ (Inflation Correction)

= 24, 000 ⇥ (80/130) 0.59 ⇥ (582/381)

= 27, 500

<latexit sha1_base64="DkgiUBxH5PRHLBA7t0QE97KkuoM=">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</latexit>

Estimation of Capital Costs 06

Total Cost of Plant

• Purchased cost - equipment f.o.b. (free on board)

• Installed cost - often 3 to 8 times larger than purchased cost

• Installed cost of equipment (Table 7.6) - 1. Direct Project Expenses

Equipment

‣ Material for installation

‣ Labor for installation

- 2. Indirect Project Expenses

‣ Freight, insurance, and taxes

‣ Construction overhead

‣ Contractor engineering expenses

(12)

Total Cost of Plant

• Installed cost of equipment (Table 7.6) - 3. Contingency and Fee

‣ Contingency

‣ Contractor fee

- 4. Auxiliary Facilities

‣ Site development

‣ Auxiliary buildings

‣ Off-sites and utilities

23

Estimation of Capital Costs 06

Lang Factors (Table 7.7)

• The cost to build a major expansion to an existing chemical plant

• Use multiplier depending on type of plant to escalate equipment costs to installed costs

F lang = 4.74 Fluid processing plant


= 3.63 Solid-fluid processing plant
 = 3.10 Solid processing plant

C T M = F lang X n

i=1

C pi

<latexit sha1_base64="7r/VPRBq9WVmPI8DKnYkcEHUFmI=">AAACD3icbVDLSsNAFJ34rPUVdelmsCiuSqKCbgqFgrgRKvQFbQyT6aQdOjMJMxOhhPyBG3/FjQtF3Lp15984bbPQ1gMXDufcy733BDGjSjvOt7W0vLK6tl7YKG5ube/s2nv7LRUlEpMmjlgkOwFShFFBmppqRjqxJIgHjLSDUW3itx+IVDQSDT2OicfRQNCQYqSN5NsnNT9t3GawAq/9lCExyGBPJdxPKay42b2Axo9p5tslp+xMAReJm5MSyFH37a9eP8IJJ0JjhpTquk6svRRJTTEjWbGXKBIjPEID0jVUIE6Ul07/yeCxUfowjKQpoeFU/T2RIq7UmAemkyM9VPPeRPzP6yY6vPJSKuJEE4Fni8KEQR3BSTiwTyXBmo0NQVhScyvEQyQR1ibCognBnX95kbTOyu552b27KFWreRwFcAiOwClwwSWoghtQB02AwSN4Bq/gzXqyXqx362PWumTlMwfgD6zPH16Rm50=</latexit>

Capital (total module) cost

Purchased cost of major equipment from preliminary PFD

(pumps, compressors, vessels, etc.) Note: Equipment Factored Estimate (EFE) 의 한 방법이다. 


cf) CFE

(13)

Module Factor Approach (Table 7.8)

• A common technique to estimate the cost of a new chemical plant introduced by Guthrie

• Also referred to as “Module Costing Technique”

• Relates all costs back to the purchased cost of equipment of base conditions

• Multiplying factors depend on -

Equipment type, Pressure, MOC

• Direct, indirect, contingency, and fees are expressed as functions (multipliers) of purchased equipment cost ( ) at base conditions (1 bar and CS)

• Details given in Appendix A

• Bare module cost = direct and indirect costs for each unit

25

C p 0

<latexit sha1_base64="cCL6hw/kWdKnyyln6BBYyBdiK30=">AAAB7HicbVBNS8NAEJ34WetX1aOXxSJ4KokKeiz04rGCaQttLJvtpl262YTdiVBCf4MXD4p49Qd589+4bXPQ1gcDj/dmmJkXplIYdN1vZ219Y3Nru7RT3t3bPzisHB23TJJpxn2WyER3Qmq4FIr7KFDyTqo5jUPJ2+G4MfPbT1wbkagHnKQ8iOlQiUgwilbyG/300e1Xqm7NnYOsEq8gVSjQ7Fe+eoOEZTFXyCQ1puu5KQY51SiY5NNyLzM8pWxMh7xrqaIxN0E+P3ZKzq0yIFGibSkkc/X3RE5jYyZxaDtjiiOz7M3E/7xuhtFtkAuVZsgVWyyKMkkwIbPPyUBozlBOLKFMC3srYSOqKUObT9mG4C2/vEpalzXvqubdX1fr9SKOEpzCGVyABzdQhztogg8MBDzDK7w5ynlx3p2PReuaU8ycwB84nz8+a45N</latexit>

Estimation of Capital Costs 06

Module Factor Approach (Table 7.8)

C BM = C p 0 F BM

<latexit sha1_base64="fQ2kgJnWnyOhQfeNptBo9G1tTFY=">AAAB/nicbVDLSsNAFL3xWesrKq7cDBbBVUlU0I1QLIgboYJ9QBvDZDpph04mYWYilFDwV9y4UMSt3+HOv3GadqGtBy6cOede5t4TJJwp7Tjf1sLi0vLKamGtuL6xubVt7+w2VJxKQusk5rFsBVhRzgSta6Y5bSWS4ijgtBkMqmO/+UilYrG418OEehHuCRYygrWRfHu/6mdXtyN0iap+8uCg6/zp2yWn7ORA88SdkhJMUfPtr043JmlEhSYcK9V2nUR7GZaaEU5HxU6qaILJAPdo21CBI6q8LF9/hI6M0kVhLE0JjXL190SGI6WGUWA6I6z7atYbi/957VSHF17GRJJqKsjkozDlSMdonAXqMkmJ5kNDMJHM7IpIH0tMtEmsaEJwZ0+eJ42Tsntadu/OSpXKNI4CHMAhHIML51CBG6hBHQhk8Ayv8GY9WS/Wu/UxaV2wpjN78AfW5w/C8ZQQ</latexit>

Bare Module Cost Purchased equipment cost for CS and 1 atm pressure (Appendix A)

Bare module factor (sum of all multipliers)

F BM = B 1 + B 2 F p F M

<latexit sha1_base64="2hn+EeTdV4Yg/kfHoO/k9Gaam30=">AAACA3icbVDLSgMxFL3js9bXqDvdBIsgCGWmCroRSoXiplDBPqAdhkyaaUMzD5KMUIaCG3/FjQtF3PoT7vwb03YW2nrghsM593JzjxdzJpVlfRtLyyura+u5jfzm1vbOrrm335RRIghtkIhHou1hSTkLaUMxxWk7FhQHHqctb3gz8VsPVEgWhfdqFFMnwP2Q+YxgpSXXPKy6aaU2Rteo4troTL8lVHVjXTXXLFhFawq0SOyMFCBD3TW/ur2IJAENFeFYyo5txcpJsVCMcDrOdxNJY0yGuE87moY4oNJJpzeM0YlWesiPhK5Qoan6eyLFgZSjwNOdAVYDOe9NxP+8TqL8KydlYZwoGpLZIj/hSEVoEgjqMUGJ4iNNMBFM/xWRARaYKB1bXodgz5+8SJqlon1etO8uCuVyFkcOjuAYTsGGSyjDLdShAQQe4Rle4c14Ml6Md+Nj1rpkZDMH8AfG5w884JSw</latexit>

F 0 BM = B 1 + B 2

<latexit sha1_base64="Wah7VRLi809Mwvirsf85YYspXOE=">AAAB/XicbVDLSgMxFL1TX7W+xsfOTbAIglBmqqAboVQQN0IF+4B2HDJppg3NPEgyQh2Kv+LGhSJu/Q93/o1pOwttPXAvh3PuJTfHizmTyrK+jdzC4tLySn61sLa+sbllbu80ZJQIQusk4pFoeVhSzkJaV0xx2ooFxYHHadMbXI795gMVkkXhnRrG1AlwL2Q+I1hpyTX3rty0ejO6t9AFqro2Ota97JpFq2RNgOaJnZEiZKi55lenG5EkoKEiHEvZtq1YOSkWihFOR4VOImmMyQD3aFvTEAdUOunk+hE61EoX+ZHQFSo0UX9vpDiQchh4ejLAqi9nvbH4n9dOlH/upCyME0VDMn3ITzhSERpHgbpMUKL4UBNMBNO3ItLHAhOlAyvoEOzZL8+TRrlkn5Ts29NipZLFkYd9OIAjsOEMKnANNagDgUd4hld4M56MF+Pd+JiO5oxsZxf+wPj8AZ9Ykrs=</latexit>

F

<latexit sha1_base64="yRstABLHGU0qtra44zNlFsKpJDs=">AAAB7HicbVBNS8NAEJ3Ur1q/qh69LBbBU0lU0GNBEI8VTFtoQ9lsN+3SzSbsToQS+hu8eFDEqz/Im//GbZuDtj4YeLw3w8y8MJXCoOt+O6W19Y3NrfJ2ZWd3b/+genjUMkmmGfdZIhPdCanhUijuo0DJO6nmNA4lb4fj25nffuLaiEQ94iTlQUyHSkSCUbSSf9fPm9N+tebW3TnIKvEKUoMCzX71qzdIWBZzhUxSY7qem2KQU42CST6t9DLDU8rGdMi7lioacxPk82On5MwqAxIl2pZCMld/T+Q0NmYSh7Yzpjgyy95M/M/rZhjdBLlQaYZcscWiKJMEEzL7nAyE5gzlxBLKtLC3EjaimjK0+VRsCN7yy6ukdVH3Luvew1Wt0SjiKMMJnMI5eHANDbiHJvjAQMAzvMKbo5wX5935WLSWnGLmGP7A+fwBszOOmg==</latexit>

P = pressure factor

F M

<latexit sha1_base64="vfiB8IJwJ+mHkXao7WoD6OeFVqk=">AAAB7HicbVBNS8NAEJ3Ur1q/qh69LBbBU0lU0GNBEC9CBWMLbSib7aRdutmE3Y1QQn+DFw+KePUHefPfuG1z0NYHA4/3ZpiZF6aCa+O6305pZXVtfaO8Wdna3tndq+4fPOokUwx9lohEtUOqUXCJvuFGYDtVSONQYCscXU/91hMqzRP5YMYpBjEdSB5xRo2V/JtefjfpVWtu3Z2BLBOvIDUo0OxVv7r9hGUxSsME1brjuakJcqoMZwInlW6mMaVsRAfYsVTSGHWQz46dkBOr9EmUKFvSkJn6eyKnsdbjOLSdMTVDvehNxf+8TmaiqyDnMs0MSjZfFGWCmIRMPyd9rpAZMbaEMsXtrYQNqaLM2HwqNgRv8eVl8nhW987r3v1FrdEo4ijDERzDKXhwCQ24hSb4wIDDM7zCmyOdF+fd+Zi3lpxi5hD+wPn8Aa6kjpc=</latexit>

= material of construction factor (= 1 for CS)

C p = C p 0 F p F M

<latexit sha1_base64="CGjSHk7vAsVi4sXTgucLGHW29jc=">AAAB/HicbZDLSgMxFIbP1Futt9Eu3QSL4KrMqKAboVAoboQK9gLtOGTSTBuayQxJRhiG+ipuXCji1gdx59uYXhZaPZDw8f/nkJM/SDhT2nG+rMLK6tr6RnGztLW9s7tn7x+0VZxKQlsk5rHsBlhRzgRtaaY57SaS4ijgtBOM61O/80ClYrG401lCvQgPBQsZwdpIvl2u+wm6Qua+d1DDcMO/8e2KU3Vmhf6Cu4AKLKrp25/9QUzSiApNOFaq5zqJ9nIsNSOcTkr9VNEEkzEe0p5BgSOqvHy2/AQdG2WAwliaIzSaqT8nchwplUWB6YywHqllbyr+5/VSHV56ORNJqqkg84fClCMdo2kSaMAkJZpnBjCRzOyKyAhLTLTJq2RCcJe//Bfap1X3rOrenldqtUUcRTiEIzgBFy6gBtfQhBYQyOAJXuDVerSerTfrfd5asBYzZfhV1sc3uk+S4A==</latexit>

(14)

27

Example-04

The purchased cost for a carbon steel heat exchanger operating at ambient pressure is $10,000. For a heat-exchanger module, Guthrie provides the following cost information:

Item % of Purchased Equip. Cost

Equipment 100.0

Materials 71.4

Labor 63.0

Freight 8.0

Overhead 63.4

Engineering 23.3

Using the information given above, determine the equivalent cost

multipliers given in Table 7.8, bare module cost factor, and bare module cost.

Estimation of Capital Costs 06

<latexit sha1_base64="haCxVaClqMn36Vfyh1iwb8F38uE=">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</latexit><latexit sha1_base64="haCxVaClqMn36Vfyh1iwb8F38uE=">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</latexit><latexit sha1_base64="haCxVaClqMn36Vfyh1iwb8F38uE=">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</latexit><latexit sha1_base64="haCxVaClqMn36Vfyh1iwb8F38uE=">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</latexit>

M = 0.714 Direct Cost: Materials

C M = ↵ M C p 0

<latexit sha1_base64="2wrM5Wj9KjndGx2EOqev8j0eTcw=">AAAB/nicbZDLSgMxFIYzXmu9jYorN8EiuCozKuhGKHTjRqhgL9COw5k004ZmMiHJCGUo+CpuXCji1udw59uYXhba+kPg4z/ncE7+SHKmjed9O0vLK6tr64WN4ubW9s6uu7ff0GmmCK2TlKeqFYGmnAlaN8xw2pKKQhJx2owG1XG9+UiVZqm4N0NJgwR6gsWMgLFW6B5Ww1t8jTvAZR8sVkP54OHQLXllbyK8CP4MSmimWuh+dbopyRIqDOGgddv3pAlyUIYRTkfFTqapBDKAHm1bFJBQHeST80f4xDpdHKfKPmHwxP09kUOi9TCJbGcCpq/na2Pzv1o7M/FVkDMhM0MFmS6KM45NisdZ4C5TlBg+tABEMXsrJn1QQIxNrGhD8Oe/vAiNs7J/XvbvLkqVyiyOAjpCx+gU+egSVdANqqE6IihHz+gVvTlPzovz7nxMW5ec2cwB+iPn8wdtTJPY</latexit>

71.4 = ↵ M 100

<latexit sha1_base64="zm7DZnBYGvYRqxefZte2tf6UJQA=">AAAB/XicbVDLSsNAFL2pr1pf8bFzM1gEVyHRQt0IBTduhAr2AW0Ik+mkHTqZhJmJUEvxV9y4UMSt/+HOv3HaZqGtBy4czrmXe+8JU86Udt1vq7Cyura+UdwsbW3v7O7Z+wdNlWSS0AZJeCLbIVaUM0EbmmlO26mkOA45bYXD66nfeqBSsUTc61FK/Rj3BYsYwdpIgX1U9ZwKukKoi3k6wMEt8lw3sMuu486AlomXkzLkqAf2V7eXkCymQhOOlep4bqr9MZaaEU4npW6maIrJEPdpx1CBY6r88ez6CTo1Sg9FiTQlNJqpvyfGOFZqFIemM8Z6oBa9qfif18l0dOmPmUgzTQWZL4oyjnSCplGgHpOUaD4yBBPJzK2IDLDERJvASiYEb/HlZdI8d7wLx7urlGu1PI4iHMMJnIEHVajBDdShAQQe4Rle4c16sl6sd+tj3lqw8plD+APr8wdj3pKa</latexit>

Direct Cost: Labor

C L = ↵ L (C p 0 + C M ) = ↵ L (1 + ↵ M )C p 0

<latexit sha1_base64="wcie0VLRPAOpImVQuzxLfoJ+h48=">AAACJnicbVDNS8MwHE39nPOr6tFLcAgTYbQq6GUw6MWDwgT3AVstaZZuYWkbklQYZX+NF/8VLx4mIt78U8y6grr5IPDy3vuR/J7PGZXKsj6NpeWV1bX1wkZxc2t7Z9fc22/KOBGYNHDMYtH2kSSMRqShqGKkzQVBoc9Iyx86U7/1SISkcXSvRpy4IepHNKAYKS15ZtXxbmAVwi5ifIA0Lzsef7DgKXS82xPt/Bi2FvObdrKYZ5asipUBLhI7JyWQo+6Zk24vxklIIoUZkrJjW1y5KRKKYkbGxW4iCUd4iPqko2mEQiLdNFtzDI+10oNBLPSJFMzU3xMpCqUchb5OhkgN5Lw3Ff/zOokKrtyURjxRJMKzh4KEQRXDaWewRwXBio00QVhQ/VeIB0ggrHSzRV2CPb/yImmeVezzin13UarV8joK4BAcgTKwwSWogWtQBw2AwRN4ARPwZjwbr8a78TGLLhn5zAH4A+PrG8ePoHY=</latexit>

63.0 = ↵ L (1 + 0.714)100

<latexit sha1_base64="dJi6LFY6MgbzwxXAN46ya9dEq0o=">AAACCXicbVC7SgNBFJ2Nrxhfq5Y2g0GICMuMCcZGCNhYWEQwD0iWZXYySYbMPpiZFcKS1sZfsbFQxNY/sPNvnCRbaOKBC4dz7uXee/xYcKUR+rZyK6tr6xv5zcLW9s7unr1/0FRRIilr0EhEsu0TxQQPWUNzLVg7lowEvmAtf3Q99VsPTCoehfd6HDM3IIOQ9zkl2kieDS/KDoJXEHaJiIfEu4UlDM8gcqq4cgoxQp5dRA6aAS4TnJEiyFD37K9uL6JJwEJNBVGqg1Gs3ZRIzalgk0I3USwmdEQGrGNoSAKm3HT2yQSeGKUH+5E0FWo4U39PpCRQahz4pjMgeqgWvan4n9dJdP/STXkYJ5qFdL6onwioIziNBfa4ZFSLsSGESm5uhXRIJKHahFcwIeDFl5dJ89zBZQffVYq1WhZHHhyBY1ACGFRBDdyAOmgACh7BM3gFb9aT9WK9Wx/z1pyVzRyCP7A+fwB205UV</latexit>

L = 0.368

<latexit sha1_base64="AISzbjnOKAw8yP7Htescf9hiNVY=">AAAB+XicbVBNS8NAEN3Ur1q/oh69LBbBU0hUtBeh4MWDhwr2A9oQJttNu3SzCbubQgn9J148KOLVf+LNf+O2zUFbHww83pthZl6Ycqa0635bpbX1jc2t8nZlZ3dv/8A+PGqpJJOENknCE9kJQVHOBG1qpjntpJJCHHLaDkd3M789plKxRDzpSUr9GAaCRYyANlJg2z3g6RCCB3yLXefyuhbYVddx58CrxCtIFRVoBPZXr5+QLKZCEw5KdT031X4OUjPC6bTSyxRNgYxgQLuGCoip8vP55VN8ZpQ+jhJpSmg8V39P5BArNYlD0xmDHqplbyb+53UzHdX8nIk001SQxaIo41gneBYD7jNJieYTQ4BIZm7FZAgSiDZhVUwI3vLLq6R14XiXjvd4Va3XizjK6ASdonPkoRtUR/eogZqIoDF6Rq/ozcqtF+vd+li0lqxi5hj9gfX5A9sjkdU=</latexit>

Similarly, multiplying factors for indirect costs (freight, overhead, and engineering) can be obtained.

F BM 0 = (1 + 0.368 + 0.047 + (1.005)(0.368) + 0.136)(1 + 0.714) = 3.291

<latexit sha1_base64="IAZQrNS1/pcDFnUogbyCYLV7YII=">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</latexit>

C

<latexit sha1_base64="s0r/zHFcso7F0upiPOstj4DhQA4=">AAACEHicbVBLS0JBFJ5rL7PXrZZthjRSEJnRoFwEkps2gUE+QE3mjqMOzn0wMzeQiz+hTX+lTYsi2rZs179pfCxK++DAx/edwznncwLBlUbo24qtrK6tb8Q3E1vbO7t79v5BTfmhpKxKfeHLhkMUE9xjVc21YI1AMuI6gtWdYXni1x+YVNz37vQoYG2X9D3e45RoI3Xs03InuroZ3yN4CdOFXL6IM+lWCqMsQihjtFaqkM8WMerYSZRDU8BlguckCeaodOyvVtenocs8TQVRqolRoNsRkZpTwcaJVqhYQOiQ9FnTUI+4TLWj6UNjeGKULuz50pSn4VT9PRERV6mR65hOl+iBWvQm4n9eM9S9i3bEvSDUzKOzRb1QQO3DSTqwyyWjWowMIVRycyukAyIJ1SbDhAkBL768TGr5HC7k8O1ZslSaxxEHR+AYpAEG56AErkEFVAEFj+AZvII368l6sd6tj1lrzJrPHII/sD5/AOaTlso=</latexit>

BM 0 = (3.291)($10, 000) = $32, 910 Solution-04

Good News!

Appendix A

(15)

29

Example-05

Find the bare module cost of a floating-head, shell-and-tube heat exchanger with a heat transfer area of 100m 2 at the end of 2011. The operating pressure of the equipment is 1.0 bar, with both shell-and-tube sides constructed of CS. From the cost curve given in Appendix A, we find that

The bare module cost for shell-and-tube heat exchangers is given by Eq. (A.4).

The values of B 1 and B 2 for the heat exchangers from Table A.4 are 1.63 and 1.66, respectively.

The pressure factor is obtained from Eq. (A.3). From Table A.2, for pressures < 5 bars, C 1 = C 2 = C 3 = 0, and thus F p = 1

From Table A.3, we also find that F M = 1 for CS.

C p 0 (2001) = ($250)(100) = $25, 000

<latexit sha1_base64="Dmm/R760GfLtFXxRKYvF4OdeTAI=">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</latexit>

C BM = C p 0 [B 1 + B 2 F p F M ]

<latexit sha1_base64="3Gmw+FQeMf24c2xIvUEB5C0Ispg=">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</latexit>

C BM (2001) = C p 0 (2001)[1.63 + 1.66 · 1 · 1] = 3.29C p 0 = (3.29)($25, 000) = $82, 300

<latexit sha1_base64="o1VpQ3euxoxnZyXjXpvTVd7+rrY=">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</latexit>

C BM (2011) = C BM 0 (2001)(582/397) = $82, 300(582/397) = $120, 650

<latexit sha1_base64="7a/Jjm5V1t8Vq7OC1yyAMl1PKho=">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</latexit>

Estimation of Capital Costs 06

log 10 C p 0 = K 1 + K 2 log 10 A + K 3 (log 10 A) 2

<latexit sha1_base64="PtuYl8sIQ9lam2E5LT5WIE6o6RU=">AAACJXicbZDLSgMxFIYz9VbrbdSlm2ARKkKZaQVdKFS7EdxUsBdop0MmzbShmQtJRihDX8aNr+LGhUUEV76K6XSQ2nog4ef7zyE5vxMyKqRhfGmZldW19Y3sZm5re2d3T98/aIgg4pjUccAC3nKQIIz6pC6pZKQVcoI8h5GmM6xO/eYT4YIG/qMchcTyUN+nLsVIKmTrVx0W9O3YNMZVO+wa8Bre2yY8U3cJ/lrwJiFlWJhDp92SreeNopEUXBZmKvIgrZqtTzq9AEce8SVmSIi2aYTSihGXFDMyznUiQUKEh6hP2kr6yCPCipMtx/BEkR50A66OL2FC5ydi5Akx8hzV6SE5EIveFP7ntSPpXlox9cNIEh/PHnIjBmUAp5HBHuUESzZSAmFO1V8hHiCOsFTB5lQI5uLKy6JRKprlovlwnq/cpnFkwRE4BgVgggtQAXegBuoAg2fwCt7BRHvR3rQP7XPWmtHSmUPwp7TvH7mLoHI=</latexit>

Equipment cost vs.

capacity (area)

Equipment Factored Estimate

의 한 방법 (Cost Curve를 이용한 C

p0

구하기) log-log 차트에서 2차함수:

꽤 정확함

Equipment Cost: a useful software tool in a book by Peters, Timmerhaus, … CAPCOST: more accurate estimating software by Turton et al.

Figure 7.4

(16)

Calculation Algorithm of BMC

Obtain C p0 (Appendix A)

Obtain F p and F m (Appendix A)

Obtain F BM (Appendix A)

• Calculate C BM

• Update cost from Sept. 2001 (CEPCI = _______)

31

Estimation of Capital Costs 06

Module Factor Approach - Pressure Factors

• Basis: ASME code

• Pressure parameter F p,vessel for a vessel having diameter D and operating pressure P (barg)

• Assuming allowable stress of carbon steel as 944 bar and welding efficiency as 90%, minimum allowable vessel thickness as 1/4” (0.0063m) and an additional thickness for allowable corrosion as 1/8” (0.00315)

F p,vessel = 1.0

<latexit sha1_base64="3dBcb0JhyqDC8qcA+/36bZwErVI=">AAACAnicbVDLSgNBEJz1GeMr6km8DAbBg4RdFfQiBATxGME8IFmW2UknGTL7YKY3GJbgxV/x4kERr36FN//GSbIHTSxoKKq6Z7rLj6XQaNvf1sLi0vLKam4tv76xubVd2Nmt6ShRHKo8kpFq+EyDFCFUUaCERqyABb6Eut+/Hvv1ASgtovAehzG4AeuGoiM4QyN5hf0bL20hPGAanwxAm4dGI3pFnZLtFYp2yZ6AzhMnI0WSoeIVvlrtiCcBhMgl07rp2DG6KVMouIRRvpVoiBnvsy40DQ1ZANpNJyeM6JFR2rQTKVMh0on6eyJlgdbDwDedAcOenvXG4n9eM8HOpZuKME4QQj79qJNIihEd50HbQgFHOTSEcSXMrpT3mGIcTWp5E4Ize/I8qZ2WnLOSc3deLJezOHLkgBySY+KQC1Imt6RCqoSTR/JMXsmb9WS9WO/Wx7R1wcpm9sgfWJ8/JIGWlg==</latexit>

when, t < t min (0.0063 m)

<latexit sha1_base64="DalhFJSViJ3p5NN+TXHI3cpI9kw=">AAACCXicbVA9SwNBEN2LXzF+RS1tFoMQm3BnRC0sAjaWEcwHJCHsbTbJkt29Y3dODEcsbfwrNhaK2PoP7Pw37iVXaOKDgcd7M8zM80PBDbjut5NZWl5ZXcuu5zY2t7Z38rt7dRNEmrIaDUSgmz4xTHDFasBBsGaoGZG+YA1/dJX4jTumDQ/ULYxD1pFkoHifUwJW6uYx4EsM3bgtuZrgolty3bMyfmgDu4dYTo5xN19IxAR4kXgpKaAU1W7+q90LaCSZAiqIMS3PDaETEw2cCjbJtSPDQkJHZMBalioimenE008m+MgqPdwPtC0FeKr+noiJNGYsfdspCQzNvJeI/3mtCPoXnZirMAKm6GxRPxIYApzEgntcMwpibAmhmttbMR0STSjY8HI2BG/+5UVSPyl55ZJ3c1qoVNI4sugAHaIi8tA5qqBrVEU1RNEjekav6M15cl6cd+dj1ppx0pl99AfO5w89s5gj</latexit>

and P >

<latexit sha1_base64="fZkuEAWlu1Y57ks2pWpdxfEwE84=">AAAB/nicbVDLSsNAFJ3UV62vqLhyM1gEN4bEB7qSghuXFewD2lAm00k7dDIJMzdiCRV/xY0LRdz6He78G6dtFtp64MLhnHu5954gEVyD635bhYXFpeWV4mppbX1jc8ve3qnrOFWU1WgsYtUMiGaCS1YDDoI1E8VIFAjWCAbXY79xz5TmsbyDYcL8iPQkDzklYKSOvVfFV/jYdc7xYxvYA2QBUb1Rxy67jjsBnideTsooR7Vjf7W7MU0jJoEKonXLcxPwM6KAU8FGpXaqWULogPRYy1BJIqb9bHL+CB8apYvDWJmSgCfq74mMRFoPo8B0RgT6etYbi/95rRTCSz/jMkmBSTpdFKYCQ4zHWeAuV4yCGBpCqOLmVkz7RBEKJrGSCcGbfXme1E8c79Txbs/KlUoeRxHtowN0hDx0gSroBlVRDVGUoWf0it6sJ+vFerc+pq0FK5/ZRX9gff4AMliUXw==</latexit>

0.5 barg

(17)

Module Factor Approach - Pressure Factors

33

when, t > t

<latexit sha1_base64="O1gunfHUeVOzhXEDNyNke87sj2Y=">AAAB83icbVBNS8NAEJ3Ur1q/qh69LBbBU0lU0JMUvHisYD+gCWWz3bRLN5uwOxFK6N/w4kERr/4Zb/4bt20O2vpg4PHeDDPzwlQKg6777ZTW1jc2t8rblZ3dvf2D6uFR2ySZZrzFEpnobkgNl0LxFgqUvJtqTuNQ8k44vpv5nSeujUjUI05SHsR0qEQkGEUr+UhuCfZzPxZq2q/W3Lo7B1klXkFqUKDZr375g4RlMVfIJDWm57kpBjnVKJjk04qfGZ5SNqZD3rNU0ZibIJ/fPCVnVhmQKNG2FJK5+nsip7Exkzi0nTHFkVn2ZuJ/Xi/D6CbIhUoz5IotFkWZJJiQWQBkIDRnKCeWUKaFvZWwEdWUoY2pYkPwll9eJe2LundZ9x6uao1GEUcZTuAUzsGDa2jAPTShBQxSeIZXeHMy58V5dz4WrSWnmDmGP3A+fwB5j5FQ</latexit>

min and P >

<latexit sha1_base64="fZkuEAWlu1Y57ks2pWpdxfEwE84=">AAAB/nicbVDLSsNAFJ3UV62vqLhyM1gEN4bEB7qSghuXFewD2lAm00k7dDIJMzdiCRV/xY0LRdz6He78G6dtFtp64MLhnHu5954gEVyD635bhYXFpeWV4mppbX1jc8ve3qnrOFWU1WgsYtUMiGaCS1YDDoI1E8VIFAjWCAbXY79xz5TmsbyDYcL8iPQkDzklYKSOvVfFV/jYdc7xYxvYA2QBUb1Rxy67jjsBnideTsooR7Vjf7W7MU0jJoEKonXLcxPwM6KAU8FGpXaqWULogPRYy1BJIqb9bHL+CB8apYvDWJmSgCfq74mMRFoPo8B0RgT6etYbi/95rRTCSz/jMkmBSTpdFKYCQ4zHWeAuV4yCGBpCqOLmVkz7RBEKJrGSCcGbfXme1E8c79Txbs/KlUoeRxHtowN0hDx0gSroBlVRDVGUoWf0it6sJ+vFerc+pq0FK5/ZRX9gff4AMliUXw==</latexit>

0.5 barg

F p = (P + 1)D/(2 · 944 · 0.9 1.2(P + 1)) + CA t min

= (P + 1)D/(2 · 850 1.2(P + 1)) + 0.00315 0.0063

<latexit sha1_base64="MWGqf9jjHpfxf06gPRSVKLb6eyo=">AAACc3icdZFda9swFIZl76vLPppt0Jte7NBsI6XUs5J0bWGDjo6xywyWthAHIytyKyrLRjoeBOM/sJ/Xu/6L3ex+cuqLLd0OCB7e8yHpPUmhpMUwvPb8O3fv3X+w9rDz6PGTp+vdZ89PbF4aLiY8V7k5S5gVSmoxQYlKnBVGsCxR4jS5PG7yp9+FsTLX33BRiFnGzrVMJWfopLj743NcwBv4AFFqGK/64x26/eltfwARn+cIh6NRS2FwCLtAgwEsa7ZhB44/1hXGVZRJXdcQRZ3/zznYC1e7wyAMh3Svrhp4N6w7cbfXYBNwG2gLPdLGOO5eRfOcl5nQyBWzdkrDAmcVMyi5EnUnKq0oGL9k52LqULNM2Fm19KyG106ZQ5obdzTCUv2zo2KZtYsscZUZwwu7mmvEf+WmJaYHs0rqokSh+c1FaakAc2gWAHNpBEe1cMC4ke6twC+YMw3dmhoT6OqXb8PJIKDDgH4d9Y7et3askU2yRfqEkn1yRL6QMZkQTn56G95LD7xf/qa/5b+6KfW9tucF+Sv83d8PYK5Q</latexit>

F p,vessel = 1.25

<latexit sha1_base64="/Vl+2AvFrfkFOhTWlI9qLgsex3A=">AAACA3icbVDJSgNBEO2JW4zbqDe9NAbBg4SZqOhBISCIxwhmgSSEnk4ladKz0F0TDEPAi7/ixYMiXv0Jb/6NneWgiQ8KHu9VdVc9L5JCo+N8W6mFxaXllfRqZm19Y3PL3t4p6zBWHEo8lKGqekyDFAGUUKCEaqSA+Z6Eite7HvmVPigtwuAeBxE0fNYJRFtwhkZq2ns3zSQ6riM8YNIHbR4aDukVdXP5s6addXLOGHSeuFOSJVMUm/ZXvRXy2IcAuWRa11wnwkbCFAouYZipxxoixnusAzVDA+aDbiTjG4b00Cgt2g6VqQDpWP09kTBf64HvmU6fYVfPeiPxP68WY/uikYggihECPvmoHUuKIR0FQltCAUc5MIRxJcyulHeZYhxNbBkTgjt78jwp53PuSc69O80WLqdxpMk+OSBHxCXnpEBuSZGUCCeP5Jm8kjfryXqx3q2PSWvKms7skj+wPn8Aoz6W0w==</latexit>

when, pressure < -0.5 barg

* For equipment other than pressure vessel,

log 10 F p = C 1 + C 2 log 10 P + C 3 (log 10 P ) 2

<latexit sha1_base64="3lwGbvzpnOvAeQpiW9pSeZd217s=">AAACI3icbZDLSgMxFIYz9VbrbdSlm2ARKkKZaQVFFAoFcVnBXqAdh0yatqGZzJBkhDL0Xdz4Km5cKMWNC9/FdDpIbT2Q8PP955Cc3wsZlcqyvozMyura+kZ2M7e1vbO7Z+4fNGQQCUzqOGCBaHlIEkY5qSuqGGmFgiDfY6TpDatTv/lEhKQBf1CjkDg+6nPaoxgpjVzzqsOCvhvb1vjWDeENrLo2PNN3Cf4asJaQMizModPHkmvmraKVFFwWdiryIK2aa0463QBHPuEKMyRl27ZC5cRIKIoZGec6kSQhwkPUJ20tOfKJdOJkxzE80aQLe4HQhyuY0PmJGPlSjnxPd/pIDeSiN4X/ee1I9S6dmPIwUoTj2UO9iEEVwGlgsEsFwYqNtEBYUP1XiAdIIKx0rDkdgr248rJolIp2uWjfn+cr12kcWXAEjkEB2OACVMAdqIE6wOAZvIJ38GG8GG/GxPictWaMdOYQ/Cnj+wd/g5/T</latexit>

Estimation of Capital Costs 06

Module Factor Approach - Material Factors

Material Factor, F M

Material F M

Carbon Steel 1.0

Stainless Steel Clad 1.7

Stainless Steel 3.1

Nickel Clad 3.6

Nickel 7.1

Titanium Clad 4.7

Titanium 9.4

(18)

35

Example-06

Compare costs for shell-and-tube heat exchanger in 2011 with an area = 100m 2 for

Carbon Steel at 1 bar Carbon Steel at 100 bar Stainless Steel at 1 bar Stainless Steel at 100 bar

Estimation of Capital Costs 06

Solution-06

P MOC C p0 C p

(=C p0 F p F m ) C BM0 C BM

1 bar CS 36.6 36.6 120.7 120.7

1 bar SS 36.6 99.9 120.7 225.8

100 bar CS 36.6 50.6 120.7 143.8

100 bar SS 36.6 138.2 120.7 289.3

F m = 2.73, F p = 1.383

<latexit sha1_base64="WMgf2eLjGFtrlr50z0Z2GNVP8pM=">AAACAnicdVDLSsNAFJ3UV62vqCtxM1gEFxKSRmi6EApCcVnBPqANYTKdtEMnD2YmQgmtG3/FjQtF3PoV7vwbpw/B54ELZ865l7n3+AmjQprmu5ZbWl5ZXcuvFzY2t7Z39N29pohTjkkDxyzmbR8JwmhEGpJKRtoJJyj0GWn5w4up37ohXNA4upajhLgh6kc0oBhJJXn6Qc0L4TksGWX7dDKBNS9RL8uwHdvTi6ZhVhzTrsDfxDLMGYpggbqnv3V7MU5DEknMkBAdy0ykmyEuKWZkXOimgiQID1GfdBSNUEiEm81OGMNjpfRgEHNVkYQz9etEhkIhRqGvOkMkB+KnNxX/8jqpDBw3o1GSShLh+UdByqCM4TQP2KOcYMlGiiDMqdoV4gHiCEuVWkGF8Hkp/J80S4ZlG9bVWbHqLOLIg0NwBE6ABcqgCi5BHTQABrfgHjyCJ+1Oe9CetZd5a05bzOyDb9BePwBL4pQl</latexit>

(19)

Total-Module Costs & Grass-Roots Costs

37

C T M = 1.18 X

all equip.

C BM

<latexit sha1_base64="4olfp0rLfe6vXDhFpF8xs2qHzEQ=">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</latexit>

TM – Includes Contingency and Fees at 15% and 3% of BM

GR – grass-roots cost includes costs for auxiliary facilities Auxiliary facilities = 50% of C BM

C GR = 0.50 X

all equip.

C BM 0 + C T M

<latexit sha1_base64="Heo+wwtmmWw4rWXNQSGGZAejMDg=">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</latexit>

Use base BM costs in GR cost (1 atm and CS) since auxiliary facilities should not depend on pressure or M.O.C.

Estimation of Capital Costs 06

Materials of Construction

• Very important

• Table 7.9 - rough guide

• Perry’s Chemical Engineer’s

Handbook - good source

(20)

Capcost

• Calculates costs based on input

• CEPCI – use current value of 542 or latest from

Chemical Engineering

• Program automatically assigns equipment numbers

39

https://richardturton.faculty.wvu.edu/publications/analysis-synthesisand-design-of-chemical-processes-5th-edition

참조

관련 문서

The “Asset Allocation” portfolio assumes the following weights: 25% in the S&amp;P 500, 10% in the Russell 2000, 15% in the MSCI EAFE, 5% in the MSCI EME, 25% in the

X-test was conducted to determine if there would be significant differences in students' addiction to Internet according to gender, academic department, the

It would be reasonable as a teacher to make efforts not only to reflect on the class on their own, but also to improve the teacher's teaching expertise

This study was carried out to select superior soybean cultivars for forage production and to determine the optimum plant density and phosphate rate for

If the information related to schools and education were opened, schools would compete to be recognized as a good school, and students could get better education.. Since

This would be the actual volume flow rate that you could observe if the pipework after the compressor was transparent and you measure the actual flow rate under

Positioning strats with a product. Positioning is what you do to the mind of the prospect. That is, you position the product in the mind of the prospect..

To obtain data for the optimal growth conditions for crops in this intelligent plant growing system, sensors were used to measure and control the