Who is KHNP?
▶ KHNP: Korea Hydro & Nuclear Power Company
- Korea’s largest power generator and the sole utility for nuclear power
▶ Established: April 2001 (separated from KEPCO)
▶ Facilities: 82 [Nuclear(24), Pumped Storage (51), and Renewable (7)]
▶ Employees: 10,107 (as of June 2015)
Credit Ratings : Moody’s (Aa3/Positive), S&P (A+/Stable), Fitch (AA-/Stable)
3
Seoul
In Operation
Under Construction Planned
(As of June 2015)
5 KORI 1
1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020 2025
KORI 3,4 HBN 1,2
HBN 3,4
HUN 3,4 WSN 2,3,4
HBN 5,6
HUN 5,6
SKN 1,2 SWN 1
SWN 2 SKN 3,4
SHN 1,2
SKN 5,6 SHN 3,4
p
O
C32
28
24
9
3
PWR PHWR
APR1400
OPR1000+
OPR1000 (KSNP)
Component Approach
Turn-Key
TMI
(1979)
KORI 2 WSN 1
HUN 1,2
Chernobyl
(1986)
Fukushima
(2011)
PWR 1400MW X 4
PWR 1000MW X 4
PWR 1000MW X 8 PHWR 600MW X 3
PWR 900MW X 6
PWR/PHWR 600MW X 3
* P : Planned, O : Operation, C : Construction
7
Part 1 Overview of the Fukushima Accident
Fukushima #1
Fukushima#2
√ distance from epicenter / resistance to earthquake(g) : 150km / 0.37g
√ distance from epicenter / resistance to earthquake(g) : 160km / 0.37g
NPP Rx SFS Contai-
nment R/B
1 M AN I F
2 M AN F I
3 M AN I F
4 No-Fuel AN No-Fuel F
* M : Molten, AN : Abnormal, I : Integrity, F : Fail
9
Automatic Rx trip Start-up of EDG
EDG
Turbine Building
Reactor Building
Earthquake occurred
1
Hydrogen explosion
4
Fuel overheated
from the loss of cooling
3
Station blackout
due to Tsunami
1 2
②
④
③
* Root Cause : Failure of reactor cooling due to station blackout
* EDG : Emergency Diesel Generator
Part 2 Post-Fukushima Measures
11
14 member countries and 20 regulatory experts
Reviewed the Korean regulatory system (July 10- 22, 2011) 44 internal & external experts
Integrity of 4 critical areas of the plant - On/Off-site power and core cooling - Containment and spent fuel pool
73 external experts and regulatory body Inspectors (for 21 nuclear units in operation)
* IRRS : Integrated Regulatory Review Service
Government’s direct involvement in the post- Fukushima measures
An independent organization under the direct control by the President of Korea
Strengthens the national radiation emergency and disaster response
Safety-First corporate policy
Role reinforcement for nuclear safety
& disaster response
Running a Post-Fukushima TFT
13
46 items
Joint Government-KHNP Team Identified (considering maximum earthquakes and tsunamis)
10 items
KHNP added
(from self-checks and overseas experiences)
Year ‘11 ‘12 ‘13 ‘14 ‘15 Total
Safety Check
(Government) 4 18 8 4 12
46
Additional
(KHNP) - 2 - 3 5
10
Total 4
(Finished) 20
(Finished) 8
(Finished) 7
(Finished) 17
(4Finished)
56
56 Items
Emergency Response
Additional radiation protective equipment for the sake of residents
11
Earthquakes and Tsunamis
ASTS
Height extension of NPP sea wall
20
Severe Accidents
Passive hydrogen removal
equipment or ventilation facilities in the CV
Reinforcement of the SAMGs
10
Electrical Power and Cooling Ability
Mobile generator vehicles
Injection loop for SFP emergency cooling water
15
15
2012
2013
2014
2015
Extension of the sea-wall of Kori NPP
Ensuring countermeasures when the cooling function of SFP is lost
Reinforcing the radiation emergency training
Improving plant seismic capacity
(e.g. seismic event alarm window in the control room)
Investigating design basis of the sea water level of sites
Preparing inundation prevention and restoration methods for loss of ultimate heat sink
Installing passive hydrogen removal equipment
Evaluating protective measures for residents
Reinforcing the performance of emergency alarm facilities
Installing ventilation or depressurizing facilities in the CV
Installing conduits for injecting nuclear reactor emergency cooling water from external sources
* CV : Containment Vessel
Part 3 Major Improvements
17
Sea
wall Water-proof Door
Diesel-driven Pump
PAR
CFVS
Reactor Emergency Cooling
SFP Emergency cooling
Mobile Generator REACTOR
Building
REACTOR Steam
Generator
EDG
SEA
① Height extension of the seawall at NPP
② Waterproof doors
③ Waterproof drain pumps (diesel-driven)
④ Mobile generator vehicles
⑤ External injection emergency cooling loop
⑥ Injection loop for SFP
⑦ Passive hydrogen removal equipment
⑧ Vent or depressurizing facilities
Installed Automatic Seismic Trip System in the 24 NPPs in Korea
- Incorporate automatic reactor shutdown system for earthquakes exceeding a certain seismic level (0.18g)
ASTS ensures a reactor is always tripped upon an occurrence of
the SSE, and yet prevents spurious trips during normal plant operations.
Raised seawall heights of Kori NPP to the height level of other NPP sites reflecting evaluation results
Installed waterproof gates and waterproof drainage pumps in major structures to prevent possible inundation
19
5.8m 7.5m
E.L 5.8m E.L 7.5m E.L 10.0m 2.5m
Equipped one vehicle-mounted emergency generator per site in a safe place and secure separate DC control power for flooding
Expanded the fuel supply capacity of an alternative emergency diesel generator considering multi-unit failure
Capacity : 3.2MW
21
Installed a connection point at SFP building so as to allow a fire engine to inject water to the spent fuel pool
- The importance of the cooling of spent fuel and the need to secure additional SFP
cooling injection
Installed PAR that can operate without any power supply based on earthquakes DBA and equipment survivability & equipment operability in SA
Installed CFVS within a containment building
NPP DBA SA
Total
L M S L M S
Kori (3 units) 4 4 - 42 10 10 70 Hanbit (6 units) 12 - - 70 52 8 142 Hanul (6 units) 12 - - 82 76 - 170 Wolsong (3 units) - 6 12 12 39 24 105
* PAR : Passive Autocatalytic Recombines, DBA(Design Base Accident), CFVS : Containment Filtered Vent System)
23
* SBO (Station Blackout), LUHS (Loss of Ultimate Heat Sink)
Areas
Guideline
①Earthquake ②Tsunami ③Loss of Safety Functions(SBO+LUHS)
④Severe accident Management ⑤Emergency response
NSSC ‘s Stress Test Specifications of (2013.04.30)Operator
Self-Assessment
① Adequacy Reviews
(including plant walk-down)
② Detailed Reviews
(regulator + private experts)
NSSC Reviews
Step 1 Step 2 Step 3
‘13.9.1
Step 1 Step 2
‘13.12.20 In progress
KORI-1
COD : 1978
‘13.5.1
Step 2
Step 1 Step 3
‘13.7.12 ‘14.12.12 ‘15.2.27
WOLSONG-1
COD : 1983
Test Area
Earthquakes Floods
Loss of safety functions (SBO+LUHA)
Severe accidents
Earthquakes Floods
Loss of safety functions (SBO+LUHA)
Severe accidents
Emergency Response
Main Inspector
NPP operator NPP operator & Regulatory Body
Results Review &
Suggestions
Regulatory Body Regulatory Body
25
YEAR 2015 2016 2017 2019 2020 TOTAL
Equipment
Reinforcement 1 3 4 1 - 9
System
Improvement - 1 1 - - 2
Long-term
Studies 2 1 2 1 2 8
SUM 3 5 7 2 2 19
These 19 items do not require immediate actions to secure Wolsong #1
NPP’s life extension, but are recommended to improve its long-term safety.
KHNP has established a long-term safety improvement plan
and its response capacity for extreme natural disasters will be strengthened.
Part 4 Safety Enhancement Plan
27
Government: 46 items KHNP: 10 items
Post-Fukushima Measures
Enhanced response for Extreme Natural
Disasters
2012
2015
21 items of 5 categories Emergency response team Emergency response center Follow-up of Stress Tests
Enhanced response for Multi-unit Accidents
2013
2014
Securing Response of BDBA Evaluation of plant status Reinforcement of fire response equipment Reinforcement of mobile equipmentEnsuring plant safety in Every Type of Disasters
2015
2020
Quantitative real-time assessment of the safety level Performance monitoring/maintaining of main system
Comprehensive Nuclear Safety Assessment (Reflection of plant operation condition)
Re-check the safety of the latest technical standard
Check the next 10 years to secure safety
Perform impact mitigation measures, in preparation for severe accident
Development of SAMG for lower power operation during shutdown period
Development of connection guideline between EOP and SAMG
Prevent ion Mitiga tio n
Shot-term (real-time)
Mid-term (5~10year)
Long-term (10year)
Emergency
response
29
Part 5 Summary
Control the Electric Power
Step 1* Step 2*
▪ ASTS
▪ Mobile generator vehicle
▪ Waterproof door
▪ Raised seawall height
▪ (+) mobile cars (multi units)
▪ Improve firefighting abilities
▪ (+) power and instruments (PHWR, SCR)
Core Cooling
Step 1 Step 2
▪ External injection line (Core, SFP)
▪ Seismic resistance(↑) - core cooling equipment
▪ (+) mobile pumps
▪ Additional supplements (SFP cooling capacity)
Contain the F.P inside C.V Communication, Culture, etc.
Step 1 Step 2
▪ Secure additional equipment
(prolonged emergency)
▪ Improve emergency response facilities
▪ Reinforce emergency alarm facilities
▪ Secure emergency response organization
▪ Secure emergency response facility
▪ Secure
communication for long-term power loss
Step 1 Step 2
▪ CFVS(PHWR)
▪ PAR
▪ Revise SMAG
▪ SAMG
(Low-Power Shutdown)
▪ CFVS(PWR)
▪ SAMG
(Long-term Shutdown)